91 four-car medium-capacity trainsets were purchased by LTA for the Thomson-East Coast line in 2014 and the first set was delivered on 25 May 2018.[7][3]
Seven additional trains were supposed to be procured for the RTS Link as both the Singapore and Malaysian governments agreed to both lines sharing largely identical technical specifications.[8] Since then, a new agreement signed on 30 July 2020 meant that these trains would not be built and will be replaced by LRT trains.
Tender
The tender for trains under the contract turnkey 251 was closed on 15 November 2013 with six bids. The Land Transport Authority has shortlisted all of them and the tender results were published on 28 May 2014.[9][10]
Kawasaki will be responsible for the overall project management, design, manufacturing of bogies and procurement of major components. CRRC Qingdao Sifang will be in charge of manufacturing, final fitting and assembly of complete MRT trains and factory testing. Kawasaki (Singapore) will be responsible for the delivery of complete MRT trains to the depot, on-site testing and commissioning.[3]
Design and features
The T251 trains have a livery of yellow and burnt sienna stripes running around the cars, similar to C951(A) trains, which bear cerulean blue and blue stripes. They include several features unique to this rolling stock, such as:[11]
A Dynamic Route Map Display (DRMD), which is termed "Train Vision" and supplied by Mitsubishi Electric;
Perch seats which are located at the ends of each train car;
Tip-up seats in 61 of the 91 trainsets;
10 doors per car (5 per side)
Two of the T251 trains, sets 2012 and 2013 were equipped with automatic track inspection system, found specifically on cars 20123 and 20133. This system includes cameras, lasers, and sensors to detect track defects such as rail cracks, missing fasteners, or foreign objects on the tracks.[11]
The car numbers of the trains range from 2001x to 2091x, where x depends on the carriage type. Individual cars are assigned a five-digit serial number. A complete four-car trainset consists of one trailer (T), one motor car (M) and two driving motor cars (DM1 & DM2) permanently coupled together.
The first digit is always a 2.
The second digit is always a 0.
The third digit and fourth digit identifies the set number.
The fifth digit identifies the car number, where the first car has a 1, the second has a 2, the third has a 3 and the fourth has a 4.
For example, set 2005 consists of carriages 20051, 20052, 20053 and 20054.
The award of the T251 turnkey contract to the Kawasaki Heavy Industries & CRRC Qingdao Sifang (formerly CSR Qingdao Sifang) consortium was briefly politicised in Singapore, when the defects from the relatively new C151A trains constructed by the same consortium were made public on 5 July 2016. This was after Gerald Giam from the Workers Party commenting through an official Facebook post doubting the decision by the Land Transport Authority to award the subsequent contracts, specifically both the design and supply of C151C and T251 rail cars to the same consortium in 2015.[12] This was despite the Land Transport Authority and operator SMRT Trains being officially acknowledged on the C151A crack defects as early as 2013.[13][14]