40 billion cubic metres (1.4×10^12 cu ft) per year
Diameter
56 in (1,422 mm)
The Iran–Pakistan gas pipeline, also known as the Peace pipeline, or IP Gas,[1] is an under-construction 2,775-kilometre (1,724 mi) pipeline to deliver natural gas from Iran to Pakistan.
Although construction of the pipeline began in 2011, the Pakistani government did not officially approve its work until 2024.[2][3]
History
Inception
The idea was conceived by a young Pakistani civil engineer Malik Aftab Ahmed Khan (Sitara e Jurat), a graduate of NED University, in mid-1950, when an article of his was published by the Military College of Engineering, Risalpur, Pakistan. The article Persian Pipeline also mentioned the method for its protection along the hostile territory by establishing mini battalion-size cantonments along its proposed route through Balochistan/Sindh.[4][5] The project was conceptualized in 1989 by Rajendra K. Pachauri in partnership with Ali Shams Ardekani and Sarwar Shar, former Deputy Foreign Minister of Iran. Pachauri proposed the plan to both Iranian and Indian governments. The government of Iran responded positively to the proposal. At the 2010 annual conference of the International Association of Energy Economics, Ardekani backed Pachauri's proposal.[5]
Timeline
Discussions between the governments of Iran and Pakistan started in 1995.[6] A preliminary agreement was signed in 1995. This agreement foresaw construction of a pipeline from South Pars gas field to Karachi in Pakistan. Later Iran made a proposal to extend the pipeline from Pakistan into India. In February 1999, a preliminary agreement between Iran and India was signed.[7]
In 2004 the project was revived after the UNDP's report Peace and Prosperity Gas Pipelines by Pakistani petroleum engineer, Gulfaraz Ahmed, was published in December 2003. The report highlighted benefits of the pipeline to Pakistan, India and Iran.[8]
In February 2007, India and Pakistan agreed to pay Iran US$4.93 per million British thermal units (US$4.67/GJ) but some details relating to price adjustment remained open to further negotiation.[9]
In April 2008, Iran expressed interest in the People's Republic of China's participation in the project.[10] In August 2010, Iran invited Bangladesh to join the project.[11]
In 2009, India withdrew from the project over pricing and security issues, and after signing a civilian nuclear deal with the United States in 2008.[12][13] However, in March 2010 India called on Pakistan and Iran for trilateral talks to be held in May 2010 in Tehran.[14]
On 4 September 2012, the project was announced to commence before October 2012 and be completed by December 2014.[15]
On 30 January 2013, the Pakistan's federal government approved a deal with Iran for laying the Pakistan's segment of a pipeline.[16] On 27 February 2013, the construction of the Pakistani section was agreed.[17][18] On 11 March 2013, the construction work on the Pakistani section of the pipeline was inaugurated by president of PakistanAsif Ali Zardari and president of IranMahmoud Ahmadinejad.[19][20][21] According with Javad Owji, managing director of the National Iranian Gas Company, the pipeline in Pakistan is expected to be constructed in 22 months with the participation of Iran.[22]
On 27 May 2013, Iranian deputy minister for petroleum, A. Khaledi, in a letter to the Pakistan government expressed concern over the delay in the start of the Pakistani portion of the pipeline. He said that after a government-to-government agreement between the two countries, they were supposed to select entities for the construction of the latter part of the pipeline. Pakistan still hasn't officially nominated Tadbir Energy and local sub-contractors to begin work on the Pakistani half of the pipeline.[23]
On 12 June 2013, the newly elected prime minister of Pakistan, Nawaz Sharif, allayed any fears regarding the abandonment of the project and said that the Pakistani government is committed to the fulfillment of the project and targets the first flow of gas from the pipeline in December 2014. The premier also stated that his government is planning to commit to the Turkmenistan-Afghanistan-Pakistan-India gas pipeline project as well.[24]
On 28 November 2013, a 'friendly' country anonymously offers $1 billion to help fund the pipeline. [tribune.com.pk 1]
On 25-Feb-2014, Minister for Petroleum and Natural Resources Pakistan, Shahid Khaqan Abbasi told the National Assembly that the project for the moment is off the table, he cited international sanctions as the issue, he said " In the absence of international sanctions the project can be completed within three years, but the government cannot take it any further at the moment because international sanctions against Iran are a serious issue". Pakistan will face the penalty if it failed to lay its side of pipeline till December 2014. Analysts however points at Saudi Arabia's pressure to not to carry out the project.[26]
Iran plans to abandon this pipeline project, as per April 2014 news article.[27]
During the state visit of Prime Minister Nawaz Sharif to Iran in May 2014, both the government stated to remain committed on the completion of the pipeline and also agreed to extend the completion date by one year.[28] However, on 30 May 2014, ISNA news agency quoted Iranian Deputy Oil Minister for International and Trade Affairs Ali Majedi as claiming that the deadline has not been extended as no such agreement was signed during Nawaz Sharif's visit and the deadline to complete is still December, 2014.[29]
During the year 2017, India is planning to disassociate from this pipeline project and working on cheaper independent under sea pipe line directly from Iran.[30]
As of early 2019, the project remains substantially delayed. While the Iranian section of the pipeline has been completed, the Pakistani section remains under construction and subject to renewed delays thanks to concerns about the US sanctions regime.[31][32]
On 23 February 2024, Pakistan approves construction of Iran-Pakistan gas pipeline amid fear of a potential 18 billion US dollar penalty for failing to complete the project on time.[33]
In August 2024, Iran threatened to move the case to International Court of Arbitration due to Pakistan's failure to construct the pipeline by the end of 2024.[34]
On 30 October 2024, Pakistan hired law firms to fight the potential case. [35]
As of December 2024, no case has been filed with the International Court of Arbitration.[36]
Controversies
In January 2010, the United States asked Pakistan to abandon the pipeline project. If canceling the project, Pakistan would receive assistance from the United States for construction of a liquefied natural gas terminal and importing electricity from Tajikistan through Afghanistan's Wakhan Corridor.[37] However, on 16 March 2010 in Ankara, Iran and Pakistan signed an agreement on the pipeline.[12] According to the agreement each country must complete its section by 2014.[38] In July 2011, Iran announced that it has completed construction of its section.[39] If Pakistan does not fulfill its obligation to complete the pipeline on its side by the end of 2014, it will have to pay a daily penalty of $1 million to Iran until completion.[40] On 13 March 2012 Pakistan's ministry of finance announced that private investors were showing diminished interest and that the government might have to impose a tax on consumers, or seek government-to-government arrangements with Iran, China and Russia to build the pipeline. On 29 March it was reported that officials from Pakistan's petroleum ministry would travel to Russia in early April for talks with Gazprom.[38] Then, in a 7 April article the Pakistani daily PakTribune reported that Gazprom would both finance and construct the pipeline. This would require setting aside the Public Procurement Regulatory Authority rules which require international bidding for such a large project. The Economic Coordination Committee would be asked in its next meeting to give such permission. The article also informed that the reason the private consortium no longer would contribute to the project was US opposition.[40]
On 15 April 2012, it was reported through unnamed diplomatic sources in Islamabad that Saudi Arabia was offering to deliver an "alternative package" to Pakistan if the country abandoned its cooperation with Iran. In addition to oil the package would also include a cash loan and oil facility. The news came in connection with a visit to Pakistan by the Saudi deputy foreign minister.[41]
On 1 May 2012, it was reported that Pakistan's foreign minister, Hina Rabbani Khar had said that Islamabad will not give in to US pressures to mothball the project and will finish the huge pipeline project "at any cost" and that the project was in line with the country's national interest.[42]
On 29 January 2013, US consul general Michael Dodman threatened Pakistan with economical sanctions if it does not abandon the project.[43]
In late October 2013, Sustainable Policy Development Institute published a report in which the proposed pipeline was termed as "death sentence" for Pakistan. Since the prices in the contract are linked to crude oil prices, the government "blatantly ignored the energy dynamics and its pricing while going for this deal". The gas sold to Pakistan will be higher priced than the current domestic prices of gas in the country.[44]
Route
The length of the pipeline that will be supplied from the South Pars field has been given variously as 900 kilometres (560 mi),[12] 1,035 kilometres (643 mi),[13] and 2,775 kilometres (1,724 mi).[45] It starts from Asalouyeh and stretches 1,172 kilometres (728 mi) through Iran. The Iranian section is known as Iran's seventh cross-country gas pipeline. The first 902-kilometre (560 mi) part of this section runs from Asalouyeh to Iranshahr. The second 270-kilometre (170 mi) part runs from Iranshahr to the Iran–Pakistan border.[46]
In Pakistan, the length of the pipeline is 785 kilometres (488 mi).[16] It will pass through Baluchistan and Sindh.[12] In Khuzdar, a branch would spur off to Karachi, while the main pipeline will continue towards Multan. From Multan, the pipeline may be expanded to Delhi.[47] The route in Pakistan may be changed if China will participate in the project.[48]
As there are concerns over the pipeline being attacked by Baluchi insurgents, an alternative offshore route from Iran to the maritime boundary between India and Pakistan off Kutch was proposed. According to this proposal, from there one branch was to run to Pakistan while other branch to run to Kutch.[49][50]
Technical description
The initial capacity of the pipeline was to be 22 billion cubic metres (780 billion cubic feet) of natural gas per year, which was expected to be raised later to 55 billion cubic metres (1.9 trillion cubic feet).[51] However, as a bilateral project between Iran and Pakistan, the pipeline will carry only 8.7 billion cubic metres (310 billion cubic feet) of gas per year as contracted and 40 billion cubic metres (1.4 trillion cubic feet) as a maximum capacity. The pipeline has a diameter of 56 inches (1,400 mm).[52] It is expected to cost US$7.5 billion and to be commissioned by 2013.[6][52]
It is expected that gas delivered from Iran through the pipeline will cost US$11 per million British thermal units ($38/MWh) compared to $13 per million British thermal units ($44/MWh) which is expected to be price of gas delivered through the proposed Trans-Afghanistan Pipeline and $18 per million British thermal units ($61/MWh) of imported LNG.[53]
Authorities blamed Lack of safety measures and old infrastructure for the Thursday 14 March 2019 explosion in a gas pipeline near the city of Mahshahr in southern Iran. One child, one woman and two others were killed in the explosion.[54]
Companies
In different times several companies have been interested to build the pipeline. Companies included Gazprom, BHP, National Iranian Gas Company, Petronas, and Total. A consortium consisting of Royal Dutch Shell, BG Group, Petronas and an Iranian business group had negotiated on exporting of gas from South Pars to Pakistan. From India, GAIL had been involved.[47] However, the pipeline's section in Iran was built by the National Iranian Gas Company. It used Khatam al-Anbia as a subcontractor.[46] In Pakistan, Inter State Gas Systems is responsible for the construction of the pipeline.
[55] The contract for engineering, procurement, construction and financing of the Pakistan's section was signed with Iran's Tadbir Energy. Iran agreed to provide a $500 million loan for construction payable in 20 years.[16] However, on 13-December-2013, Pakistan's Minister for Petroleum and Natural Resources Shahid Khaqan Abbasi said that Iran refused to fund the project citing 'acute financial constraint' as the reason. Pakistan authorities however said to remain committed with the project. Both sides have decided to constitute a working group which would re-establish in two months the new parameters for the projects, including a new time-frame and other important issues involving financing of pipeline to be laid down in the territory of Pakistan.[56][57]
Statue This article includes a list of references, related reading, or external links, but its sources remain unclear because it lacks inline citations. Please help to improve this article by introducing more precise citations. (December 2019) (Learn how and when to remove this template message) Virgin of OcotlánLocationOcotlán, Tlaxcala, MexicoTypeMarian statueApprovalPope Pius XPatronageMexico (Tlaxcala and Pueblo) The Virgin of Ocotlán is a statue of the Blessed Virgin Mary in Ocotlán,...
This article needs additional citations for verification. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.Find sources: St. Paul's Episcopal School – news · newspapers · books · scholar · JSTOR (September 2008) (Learn how and when to remove this template message) Private school in Mobile, Alabama, United StatesSt. Paul's Episcopal SchoolAddress161 Dogwood LaneMobile, Alabama 366...
Database manager part of the Microsoft 365 package Microsoft AccessMicrosoft Office Access 2021 running on Windows 10Developer(s)MicrosoftInitial releaseNovember 1992; 31 years ago (1992-11)Stable release(s)Microsoft 365 (Windows)2310 (Build 16924.20150)[1] / November 14, 2023; 19 days ago (2023-11-14)Microsoft 365 (Mac)16.79.1 (Build 23111718) / November 21, 2023; 12 days ago (2023-11-21)[2]One-time purchase (Retail)2...
Ulrich von Cilli Wappen von Ulrich II. Ulrich II. von Cilli (auch Cilly oder Cili; * 1406, in Celje[1]; † 9. November 1456 in Belgrad[1]) war gefürsteter Graf von Cilli und der Letzte seiner Familie, die mit ihm ausstarb. Inhaltsverzeichnis 1 Herkunft, Familie und Kinder 2 Leben 2.1 Anfänge 2.2 Unter der Herrschaft von König Ladislaus Postumus 2.3 Der Tod und dessen Folgen 3 Beurteilung 4 Rezeption 5 Literatur 5.1 Lexikon-Artikel 5.2 Quellen 6 Weblinks 7 Einzelnachweise H...
NeptunbrunnenSchlossbrunnen, Begasbrunnen Gesamtansicht des Neptunbrunnens Gesamtansicht des Neptunbrunnens Ort Berlin-Mitte Land Deutschland Verwendung Brunnen Bauzeit 1888–1891 Architekt Reinhold Begas Baustil Neobarock Technische Daten Höhe 10 m Durchmesser 18 m Grundfläche 250 m² Baustoff Roter Granit, Bronze Koordinaten Lage 52.51972222222213.406666666667Koordinaten: 52° 31′ 11″ N, 13° 24′ 24″ O52° 31′ 11″ N,...
Prasasti Untash Napirisha, batu pasir, skt. 1340-1300 SM, dibawa dari Tchoga Zanbil ke Susan pada abad ke-12 SM; wanita berekor ikan memegang ular Untash-Napirisha merupakan seorang raja Elam (sekarang Iran barat daya) selama periode Pertengahan Elam. Ia adalah putra dari raja Elam sebelumnya, Humban-Numena. Ia dinamai seperti Napir, dewa bulan Elam. Ia mendirikan dan membangun kota baru yang luas, Dur-Untash, 40 km SE dari Susan, Chogha Zanbil modern. Ia membangun secara luas di kota in...
2021 American filmUnder the VolcanoPosterDirected byGracie OttoWritten byCody GreenwoodGracie OttoIan ShadwellProduced byCody GreenwoodCinematographyHugh MillerEdited byKaren JohnsonMusic byPiers Burbrook de VereProductioncompanyRush FilmsDistributed byUniversal Home EntertainmentRelease date 19 March 2021 (2021-03-19) (SXSW) Running time90 minutesCountryUnited StatesLanguageEnglish Under the Volcano is a 2021 music documentary film by Australian filmmaker Gracie Otto. Cent...
哈萨克斯坦政府機構哈萨克斯坦国家地震观测与研究中心Қазақстандық ұлттық сейсмологиялық обсерватория және ғылыми-зерттеу орталығы(哈萨克语)機構概要成立時間1991年前身機構哈萨克科学院地震研究所[1]機構類型商业、政府機構机构驻地 哈萨克斯坦阿拉木图[2]机构首长主席:阿巴卡诺夫[3]上级机构哈萨克斯坦共...
Ethnic group of western and north-central Mexico Caxcan CazcanCaxcan warriors battling against the SpaniardsTotal populationUnknownRegions with significant populationsWestern and North-Central MexicoLanguagesCaxcan and SpanishRelated ethnic groupsOther Chichimecas Map of the Caxcan and surrounding nations during the 16th century The Caxcan are an ethnic group who are indigenous to western and north-central Mexico, particularly the regions corresponding to modern-day Zacatecas, southern Durang...
Uniwersytet Semmelweisa w BudapeszcieSemmelweis EgyetemUniversitas Budapestiensis de Semmelweis NominataSemmelweis University Dewiza Servamus Vitam Atque Servimus Data założenia 1769 Patron Ignaz Semmelweis Państwo Węgry Adres Budapeszt Liczba studentów 11 000 Rektor Béla Merkely[1] Położenie na mapie BudapesztuUniwersytet Semmelweisa w Budapeszcie Położenie na mapie WęgierUniwersytet Semmelweisa w Budapeszcie 47°29′14″N 19°04′02″E/47,487222 ...
Irish peer and Conservative politician The Most HonourableThe Marquess of WaterfordKP, PCLord Waterford by Spy (Leslie Ward), 1879.Master of the BuckhoundsIn office27 June 1885 – 28 January 1886MonarchVictoriaPrime MinisterThe Marquess of SalisburyPreceded byThe Earl of CorkSucceeded byThe Lord Suffield Personal detailsBorn21 May 1844Died23 October 1895 (1895-10-24) (aged 51)NationalityBritishPolitical partyConservativeSpouse(s)(1) Florence Grosvenor Rowley (2) Lady Blanc...
Parafia św. Wawrzyńca Kościół św. Wawrzyńca w Starym Waliszowie Państwo Polska Siedziba Stary Waliszów Adres Stary Waliszów 357-500 Bystrzyca Kłodzka Wyznanie katolickie Kościół rzymskokatolicki Diecezja świdnicka Dekanat Bystrzyca Kłodzka Filie Stary Waliszów Krzyża św. i Nowy Waliszów św. Mikołaja Proboszcz ks. Krzysztof Krauzowicz Wezwanie św. Wawrzyńca Wspomnienie liturgiczne 26 lipca Położenie na mapie gminy Bystrzyca KłodzkaParafia św. Wawrzyńca Poło...
Association football league in Uzbekistan Football leagueUzbekistan Super LeagueOʻzbekiston SuperligasiOrganising bodyUzbekistan Professional Football LeagueUzbekistan Football AssociationFounded1992; 31 years ago (1992)CountryUzbekistanConfederationAFCNumber of teams14Level on pyramid1Relegation toUzbekistan Pro LeagueDomestic cup(s)Uzbekistan CupUzbekistan Super CupLeague cup(s)Uzbekistan League CupInternational cup(s)AFC Champions LeagueAFC CupCurrent championsPakhtakor ...
Church in south Bristol, England This article does not cite any sources. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.Find sources: Counterslip Baptist Church – news · newspapers · books · scholar · JSTOR (January 2021) (Learn how and when to remove this template message) Counterslip Baptist ChurchWestern façadeReligionAffiliationBaptist ChurchLocationLocationBristol, Englan...
Breed of goat Somali goats in Ali Sabieh, Djibouti. The Somali goat is a goat breed from Somalia, Djibouti and northeast Kenya used primarily for the production of meat.[1] The animals have short ears and hair, usually white but sometimes with spots or patches.[1] Both males and females have horns, although females are often polled.[1] The goats are drought tolerant and, when milked, can each yield one to three kilograms of milk daily, even when access to water is limi...
Main article: Venkateswara Temple, TirumalaThis article may be too long to read and navigate comfortably. Please consider splitting content into sub-articles, condensing it, or adding subheadings. Please discuss this issue on the article's talk page. (October 2023) Venkateswara Temple is an important Vaishnavite temple situated in the hill town of Tirumala in Tirupati of Andhra Pradesh, India. The Temple is dedicated to Lord Venkateswara, an incarnation of Vishnu, who is believed to be appear...
«Union Jack» redirige aquí. Para el personaje de Marvel Comics, véase Union Jack (cómic). Bandera del Reino Unido Datos generalesTerritorio Reino UnidoUso Proporción 1:2Adopción 1 de enero de 1801 (222 años)12 de abril de 1606 (primer diseño)Colores Azul Rojo BlancoVariantes[editar datos en Wikidata] Bandera del Reino UnidoOpcional en tierra Datos generalesTerritorio Reino UnidoUso ...
Interstate Highway in Minnesota, United States This article is about the section of Interstate 94 in Minnesota. For the entire route, see Interstate 94. Interstate 94Blue Star Memorial HighwayPurple Heart TrailI-94 highlighted in redRoute informationMaintained by MnDOTLength259.49 mi[1] (417.61 km)NHSEntire routeRestrictionsNo hazardous goods allowed in the Lowry Hill TunnelMajor junctionsWest end I-94 / US 52 at the North Dakota state lineMajor intersect...
UK competitive sports team For the men's team, see England national rugby sevens team. This article needs to be updated. Please help update this article to reflect recent events or newly available information. (June 2021) Rugby teamEnglandUnionRugby Football UnionEmblem(s)Red RoseCoach(es)Simon MiddletonCaptain(s)Michaela Staniford Team kit Change kit World Cup SevensAppearances2 (First in 2009)Best result5th place, 2009 Team England at the 2022 Commonwealth Games. The English women's nationa...