UK market support mechanism for low carbon electricity generation
Contracts for Difference (CfD) are the main market support mechanism for low carbon electricity generation in the UK. The scheme replaced the Renewables Obligation which closed to new generation in March 2017. It is administered by the Low Carbon Contracts Company (LCCC), which is owned by the UK Government.
The scheme offers a fixed "Strike Price" to generators over a 15-year contract, which provides financial certainty, unlike the wholesale electricity market which can fluctuate significantly. With the contract for difference, if the market price for electricity drops below the Strike Price, LCCC pays the generator the shortfall, however if the market price rises, the generator must pay back the difference. The costs of the scheme are passed onto consumers via their electricity bills.[1]
The contracts are awarded using a reverse auction in annual "Allocation Rounds" (AR) where companies submit sealed bids for a project capacity and cost. Contracts are awarded to the lowest cost projects first, until a predefined budget or capacity cap is reached. The budget is split into different 'Pots' which different technologies can bid into,[2] although these have varied by auction.
Bids cannot be above a maximum "Administrative Strike Price" set before the auction.[3] To make comparison between years easier, all Strike Prices are quoted in 2012 prices, but projects are paid an inflation-adjusted amount linked to the Consumer Price Index (CPI). The projects also set out a delivery year, when the projects is expected to be commissioned, however this may slip for various reasons.[1]
History
In December 2010, the Government introduced plans to reform the electricity market.[4] The Electricity Market Reform (EMR) introduced both a capacity market to incentivise reliable generation and Contracts for Difference to provide revenue certainty to developers investing in low carbon and renewable energy, but at a lower cost that the Renewables Obligation.[5]
Prior to the first Allocation Round, there was a mechanism called Final Investment Decision Enabling for Renewables.[6] This awarded CfDs to five offshore wind projects, two biomass conversion projects, and one dedicated biomass with combined heat and power, with a total capacity of almost 4.5 GW.[6][7]
Results of the first three auctions were announced in February 2015, September 2017, and October 2019. Starting with AR4 in 2022, subsequent auctions have been on an annual basis.
In 2024, the Department for Energy Security and Net Zero (DESNZ) consulted on proposed updates to the CfD starting in AR7. Two main changes to the scheme were published in October. Firstly, Adding support for repowering of onshore wind projects after 25 years of commercial operation. Support for repowering other technologies may be added in future. Secondly, extending the phased approach for fixed offshore wind projects to floating, allowing them to be built in up-to three phases to reduce construction risk.[9][10]
The Clean Power 2030 Action Plan, published by DESNZ in December 2024, indicated further targeted reforms would be implemented before the AR7 auction, subject to further consultation. This includes reviewing the budgeting parameters for fixed offshore wind, and relaxing the eligibility criteria of requiring full planning permission for fixed offshore wind projects.[11]
In November 2024, the Clean Industry Bonus (CIB) was launched. This provides additional CfD support to offshore wind projects (both fixed and floating) that invest in more sustainable supply chains. However, to be applicable for AR7, offshore wind projects need a CIB. It will have a budget of £27m per GW of capacity in AR7, and the application process will run from 13 to 19 February 2025. The CIB was initially introduced as Sustainable Industry Rewards, but was later renamed.[12][13]
Allocation Rounds
AR1 (2014/15)
The first Allocation Round auction started in October 2014, with results announced on 19 February 2015.[14] The maximum prices are given in the first table below. A total of 2.1 GW of contracts were awarded, primarily for two offshore wind projects, the 714 MW East Anglia 1 and the 448 MW Neart Na Gaoithe, plus 15 smaller onshore wind projects.[15]
Administrative Strike Prices for AR1 by technology and delivery year (£2012/MWh)[5]
Pot/Technology
2014/15
2015/16
2016/17
2017/18
2018/19
Pot 1 (established)
Onshore Wind (>5 MW)
95
95
95
90
90
Solar photovoltaic (>5 MW)
120
120
115
110
100
Energy from Waste (with CHP)
80
80
80
80
80
Hydro (>5 MW and <50 MW)
100
100
100
100
100
Landfill gas
55
55
55
55
55
Sewage gas
75
75
75
75
75
Pot 2 (less established)
Offshore wind
155
155
1560
140
140
Tidal stream
305
305
305
305
305
Wave
305
305
305
305
305
Advanced Conversion Technologies (with or without CHP)
155
155
150
140
140
Anaerobic digestion (with or without CHP) (>5 MW)
150
150
150
140
140
Dedicated biomass (with CHP)
125
125
125
125
125
Geothermal (with or without CHP)
145
145
145
140
140
Pot 3
Biomass conversion
105
105
105
105
105
Results for AR1 by technology and delivery year [5]
Pot/Technology
Capacity (MW)
№ of
projects
Strike Price (£2012/MWh)
2015/16
2016/17
2017/18
2018/19
2015/16
2016/17
2017/18
2018/19
Pot 1 (established)
Onshore Wind (>5 MW)
—
45
77.5
626.05
15
—
79.23
79.99
82.50
Solar photovoltaic (>5 MW)
32.88
38.67
—
—
5
50.00
79.23
—
—
Energy from Waste (with CHP)
—
—
—
94.75
2
—
—
—
80.00
Pot 2 (less established)
Offshore wind
—
—
714
448
2
—
—
119.89
114.39
Advanced Conversion Technologies
—
—
36
26
3
—
—
119.89
114.39
Total
32.88
83.67
827.50
1194.80
27
—
—
—
—
AR2 (2017)
The second round ran from April to September 2017.[16] As announced in the 2016 budget, no funding was allocated in Pot 1 for the more established technologies of onshore wind, solar PV, hydro, energy from waste with CHP, landfill gas, and sewage gas. Instead, a Pot 2 budget of £290m for less established technologies, of which offshore wind was expected to form the majority.[17] Nearly 3.2 GW of contracts were awarded for three offshore wind farms: Triton Knoll (860 MW), Hornsea Project 2 (1386 MW), and Moray Offshore Windfarm (East) (950 MW). Several smaller projects for advanced conversion technologies and dedicated biomass with CHP were also funded.[18]
Parameters and results for AR2 by technology and delivery year [18][19]
Pot/Technology
ASP (£2012/MWh)
Capacity (MW)
№ of
projects
SP (£2012/MWh)
2021/22
2022/23
2021/22
2022/23
2021/22
2022/23
Pot 2 (less established)
Offshore wind
105
100
860
2336
3
74.75
57.50
ACT (standard or advanced; with or without CHP)
125
115
56.31
8
6
74.75
40.00
Anaerobic digestion (with or without CHP; >5MW)
140
135
—
—
—
—
—
Dedicated biomass (with CHP)
115
115
85.64
—
2
74.75
—
Wave
310
300
—
—
—
—
—
Tidal stream
300
295
—
—
—
—
—
Total
—
—
1001.95
2344
11
—
—
AR3 (2019)
The auction process for AR3 took place between May and September 2019, with results announced in October. Of the £265m annual budget, £200m was for offshore wind, £24m for floating offshore wind, and £10m for onshore wind, with the remaining £31m for other less established technologies including (onshore) remote island wind.[20] AR3 delivered record low prices for offshore wind, with contracts to deliver in 2023/24 came in at £39.650/MWh and those delivering in 2024/25 at £41.611/MWh.[21]
Parameters and results for AR3 by technology and delivery year [22][23]
Pot/Technology
ASP (£2012/MWh)
Capacity (MW)
№ of
projects
SP (£2012/MWh)
2023/24
2024/25
2023/24
2024/25
2023/24
2024/25
Pot 2 (less established)
Advanced Conversion Technologies
113
111
27.5
6.1
2
39.65
41.611
Anaerobic digestion (>5 MW)
122
121
—
—
—
—
—
Dedicated biomass with CHP
121
121
—
—
—
—
—
Geothermal
129
127
—
—
—
—
—
Offshore wind
56
53
1212
2854
6
39.65
41.611
Remote island wind (>5 MW)
82
82
225.72
49.5
4
39.65
41.611
Tidal stream
225
217
—
—
—
—
—
Wave
281
268
—
—
—
—
—
Total
—
—
2865.22
2909.6
12
—
—
AR4 (2021/22)
The auction for AR4 took place between December 2021 and July 2022, and re-introduced Pot 1 for established technologies. Of the total £285m budget, a £20m ringfence was set aside for tidal stream projects in Pot 2,[24] and for the first time four contracts totalling just over 40 MW were awarded CfDs, MeyGen, Magallanes Renovables, and two for Orbital Marine Power.[25] The first contract for a floating offshore wind turbine was also awarded, to Hexicon AB for their 32 MW TwinHub project.[26]
Parameters and results for AR4 by technology and delivery year[27]
Pot/Technology
ASP (£2012/MWh)
Capacity (MW)
№ of
projects
SP (£2012/MWh)
All delivery years
2023/24
2024/25
2025/26
2026/27
2023/24
2024/25
2025/26
2026/27
Pot 1 (established)
Solar PV (>5 MW)
47
251.38
1958.03
—
—
66
45.99
45.99
—
—
Onshore Wind (>5 MW)
53
—
887.96
—
—
10
—
42.47
—
—
Energy from waste (with CHP)
121
—
30
—
—
1
—
45.99
—
—
Pot 2 (less established)
Tidal stream
211
—
—
5.62
35.2
4
—
—
178.54
178.54
Floating offshore wind
122
—
—
—
32
1
—
—
—
87.30
Remote Island Wind (RIW)
62
—
—
—
597.6
6
—
—
—
46.39
Offshore Wind
46
—
—
—
6994.34
5
—
—
—
37.35
Total
—
251.38
2875.99
5.62
7659.14
93
—
—
—
—
AR5 (2023)
The auction for AR5 took place between March and September 2023. The available budget was £170 million for Pot 1 (established technologies) and £35 million for Pot 2 (emerging technologies) including a minimum £10m ringfence for tidal stream.[28] Despite warnings from industry before the auction, there were no bids from offshore wind projects as the Administrative Strike Price was seen to be to low to cover the increases in supply chain and cost of capital.[29]
Parameters and results for AR5 by technology and delivery year [30][31]
Pot/Technology
ASP (£2012/MWh)
Capacity (MW)
№ of
projects
SP (£2012/MWh)
All delivery years
2025/26
2026/27
2027/28
All delivery years
Pot 1 (established)
Energy from waste (with CHP)
116
—
—
—
—
—
Hydro (>5MW and <50MW)
89
—
—
—
—
—
Landfill gas
62
—
—
—
—
—
Offshore wind
44
—
—
—
—
—
Onshore wind (>5 MW)
53
31.1
204.4
1245.24
24
52.29
Remote island wind (>5 MW))
53
—
—
223.6
1
52.29
Sewage gas
148
—
—
—
—
—
Solar PV (>5 MW)
47
393.96
150.74
1382.98
56
47.00
Pot 2 (less established)
Advanced Conversion Technologies
182
—
—
—
—
—
Anaerobic digestion (>5 MW)
136
—
—
—
—
—
Dedicated biomass with CHP
162
—
—
—
—
—
Floating offshore wind
116
—
—
—
—
—
Geothermal
119
—
7
5
3
119.00
Tidal stream
202
—
4.5
48.54
11
198.00
Wave
245
—
—
—
—
—
Total
—
425.06
366.64
2905.36
95
—
AR6 (2024)
The auction for AR6 took place between March and September 2024. The budget was initially set at just over £1bn.[32][33] Following the election, at the end of July, the budget for AR6 was increased by 50% to £1.555bn.[34][35] The budget was split into three pots by technology:[33]
Pot 1 for established technologies, initially £120m, increased to £185m,
Pot 2 for emerging technologies, initially £105m, increased to £270m (again including a ringfence for tidal stream, of £10m then £15m)
Pot 3 for offshore wind, initially £800m, increased to £1.1bn.
The Administrative Strike Prices were significantly increased from AR5. The Contracts for Difference Allocation 6 results were announced on 3 September 2024, with 131 projects being awarded contracts.[36][37]
Parameters and results for AR6 by technology and delivery year [33][36]
Pot/Technology
ASP (£2012/MWh)
Capacity (MW)
№ of
projects
SP (£2012/MWh)
All delivery years
2026/27
2027/28
2018/29
All delivery years
Pot 1 (established)
Energy from waste (with CHP)
181
—
—
—
—
—
Hydro (>5MW and <50MW)
102
—
—
—
—
—
Landfill gas
69
—
—
—
—
—
Onshore wind (>5 MW)
64
272.58
717.79
—
22
50.90
Remote island wind (>5 MW))
64
—
—
—
—
—
Sewage gas
162
—
—
—
—
—
Solar PV (>5 MW)
61
1091.54
2196.77
—
93
50.07
Pot 2 (less established)
Advanced Conversion Technologies
210
—
—
—
—
—
Anaerobic digestion (>5 MW)
144
—
—
—
—
—
Dedicated biomass with CHP
179
—
—
—
—
—
Floating offshore wind
176
—
—
400
1
139.93
Geothermal
157
—
—
—
—
—
Tidal stream
261
—
10
18
6
172.00
Wave
257
—
—
—
—
—
Pot 3 (offshore wind)
Offshore wind
73
—
—
3363.07
2
58.87
Offshore wind permitted reduction*
n/a
—
1578.51
—
7
54.23
Total
—
1364.12
4503.07
3781.07
131
—
* offshore wind permitted reduction refers to projects that had a previously secured CfD, but have now been awarded a CfD at a higher price. The original contract allowed for up to 25% of the capacity to be withdrawn.[37]
AR7 (2025)
The seventh Allocation Round auction is expected to happen in 2025. Prior to this, the Clean Industry Bonus applications will take place in February 2025.
Generating capacity awarded
Capacity awarded (MW) by technology and Allocation Round[1] (n/a signifies technology was not eligible to bid into that auction)