The Chicago Spire was a skyscraper project in Chicago that was partially built between 2007 and 2008 before being cancelled. Located at 400 N. Lake Shore Drive, it would have stood 2,000 feet (610 m) high with 150 floors and been the tallest building in the Western Hemisphere. When originally proposed as the Fordham Spire in July 2005, the design had 116 stories, included a hotel and condominiums, and was topped with a broadcast antenna mast.[6] The building was designed and spearheaded by Spanish architect-engineer Santiago Calatrava and Chicago developer Christopher T. Carley of the Fordham Company. On March 16, 2006, the Chicago Plan Commission unanimously approved the initial design of the building.[7] On November 4, 2014, a court ruling brought the original development plan and the extended litigation over the nine-year-old project to a close.[8] Developer Garrett Kelleher signed over the property location to the project's biggest creditor, Related Midwest, who announced that they would not build the Spire and released plans for a different project.[8]
Planning
Christopher T. Carley of the Fordham Company proposed the Fordham Spire in July 2005. In the proposal the Spire was to be a 116-story structure with hotel and condominiums topped by a tall broadcast antenna mast.[6] The initial design of the building was passed unanimously by the Chicago Plan Commission on March 16, 2006, and by the Chicago Zoning Committee on March 23, 2006.[7] On March 29, 2006, the Chicago City Council also approved the building's design.[9] As part of the approval process, the council passed a measure that raised the height limit on structures at the site to accommodate the 2,000-foot (610 m) design height. The Fordham Spire would have become the second tallest building in the entire world, surpassed only by the Burj Khalifa, and would have become the tallest freestanding structure as well as the tallest building in the Western Hemisphere, surpassing the CN Tower in Toronto.[10][11][12]
Chicago MayorRichard M. Daley approved of the design, stating that it was environmentally friendly. Burton F. Natarus, who was the 42nd-ward alderman when the building was announced, said, "This is a very unique opportunity for the city of Chicago. This building belongs to Chicago and should be in Chicago."[14]Donald Trump immediately voiced opposition to the building, stating that the tall structure would be a target for terrorists and did not even seem to be a viable project.[15]
Development
Initial financial problems
After several months of development in 2005, Carley failed to obtain sufficient financing for the construction of the building.[16]Irish developer Garrett Kelleher, executive chairman of Shelbourne Development Group, Inc., acquired the land and took over the project. It was announced that he would put up 100% of the equity, something Carley had been unable to do.[16][17] He also had the financial backing to acquire the land, something Carley lacked. Kelleher stated he would consider using Carley's services on the development and that "Carley will be paid an unspecified sum for his involvement in the deal so far."[18] Kelleher later renamed the project "Chicago Spire" after briefly going by "400 North Lake Shore Drive", as it was no longer a Fordham project.[18]
New designs
In the final quarter of 2006, Shelbourne Development issued two separate press releases regarding the construction and design of the spire. A November 2006 press release stated that construction of the Chicago Spire would begin in June 2007. In early December 2006, Shelbourne Development issued another press release stating that the design of the building had been revised. This included the removal of the hotel and the antenna mast, making the building consist solely of condominium units. The design change altered the building design such that it was wider than the original plan. Additionally, the spire no longer tapered at the top, resulting in an increase in floor space and overall floor count. The revision also removed the separate parking structure from the original plan, instead incorporating underground parking into the spire itself.[1] This first major redesign of the Chicago Spire was criticized by architectural critics and city officials.[19]
In late December 2006, the Chicago Tribune reported that the developer was soliciting opinions on a further revision from community leaders.[20] Several weeks following that report the Chicago Tribune held an exclusive interview with architect Santiago Calatrava and lead developer Garrett Kelleher. During the interview, Calatrava drew out design ideas restoring the rotating design of the building and showcasing his vision for the Chicago Spire's lobby.[21] On March 26, 2007, further revisions were shown during a public presentation by Shelbourne Development showcasing the most recent design.[22]
Approval
Following the March 26, 2007 public presentation by Shelbourne Development, residents showed a favorable reaction to the newest design of the Chicago Spire.[23] The Chicago Plan Commission approved the final plans of the Chicago Spire on April 19, 2007.[23][24][25] Chicago's zoning committee also approved the tower on April 26 and, on May 9, 2007, the Chicago City Council approved the final design of the Chicago Spire.[13][24]
Marketing
By June 2008, Shelbourne had sold more than 350 of the 1,193 units—more than half of those to foreign investors in markets where certain United States Securities and Exchange Commission regulations do not apply. Shelbourne announced on September 30, 2008 that the building's penthouse had been sold to Beanie Babies manufacturer Ty Warner.[26] Kelleher offered to rent out units at a guaranteed 7.5% return to spur sales. The approach is common outside the United States where the tower was marketed more heavily and was meant to spur sales of the smallest units, which are the most likely to be purchased as rental property investments by foreigners.[27]
Financial crisis and suspension of construction
By October 2008, the late-2000s recession was beginning to affect the project. Construction was suspended and the tower's architect, Santiago Calatrava, placed an $11.34 million lien on the construction site, stating that Kelleher had not yet paid him for his work.[28] Within a few months Anglo Irish Bank, the primary lender for the project, was on the brink of financial collapse.[29] The bank's stocks had lost nearly all of their value and Anglo Irish Bank was facing nationalization.[29] Due to the bank's dire financial situation, Shelbourne Development was forced to suspend construction,[30] and would eventually have to pay back the $69.5 million (USD) it had already borrowed.[29][31]
Additional litigation and liens threatened the project by autumn 2009. The owner of the NBC Tower in Chicago sued to evict Shelbourne Development from their sales office, where extensive modeling of Chicago Spire units had been installed.[32] The lawsuit alleged that Shelbourne was behind $316,000 (USD) in lease payments.[32] In addition to this and other liens listed on the property,[33]Bank of America filed a lawsuit against Shelbourne Development for $4.92 million (USD).[34] The lawsuit was an attempt to collect that sum on two unpaid loans used for initial construction at the Chicago Spire site.[34]
After these setbacks, the AFL–CIO and Kelleher announced in late 2009 that they were discussing the potential for a $170 million (USD) land loan that would retire Kelleher's loan from Anglo Irish Bank, pay off the outstanding liens, and restart work in exchange for making the construction a complete union job.[33] Due to the lack of construction and the sluggish economy, Chicago unions were desperate to find work for their employees as they faced near 30% unemployment.[31] Construction of the Chicago Spire would have provided approximately 900 full-time jobs to union members for four years if construction had resumed.[31] In addition to the $194 million (USD) that Kelleher has invested personally in the project already, backup financing of an unspecified amount and from an unknown source in the form of mezzanine capital and bridge loans has been guaranteed and would have kicked in automatically if the $170 million (USD) AFL-CIO loan had been secured.[35]
But within weeks of the official announcement that Kelleher was searching for union bailouts, four major labor union investment funds declined to offer Shelbourne Development any loans.[36] Kelleher continued to search for financing.[36] Shelbourne Development faced eviction from its offices on the 50th floor of 111 South Wacker Drive on which Shelbourne owed $27,600 in unpaid rent.[37] Earlier in the year, the spire's Chicago sales office had been ejected from the nearby NBC Tower.[38]
In October 2010 Anglo Irish Bank Corp. filed a $77 million foreclosure lawsuit against Kelleher, claiming that loans made to Kelleher's development company had been in default for a year. The bank was expected to take possession of the site.[39] By the end of the year, courts handed control of the site to a receiver, leaving the project (at the time) dead.[40][41] In addition, two Chicago firms purchased the tax lien certificates on the property.[42]
End of the project
In 2013, with the Chicago Spire site for sale by Ireland's National Asset Management Agency (NAMA),[43] interest resumed, drawing in at least a half-dozen offers for the property. Under the involuntary bankruptcy ruling in October 2013, Shelbourne had until the end of March 2014 to obtain approval of a reorganization plan, and was considering a bid to take back control of the property, reigniting hope that the skyscraper might actually be built.[44]
However, on October 31, 2014, the developer failed to make a required payment to Related Midwest and Related filed suit to compel Shelbourne to turn over the deed to the property.[45] On 4 November 2016, Garrett Kelleher signed over the property located at 400 N. Lake Shore Drive to Related Midwest. President Curt Bailey said that Related Midwest would not build the Spire.[8]
In February 2016, Shelbourne sought court approval to take up an offer of up to $135 million from Atlas Apartment Holdings intended to underpin the project's emergence from bankruptcy, with a deadline of August 31, 2016 for having a court-approved reorganization plan.[46][47] At a hearing on March 11, 2016, Shelbourne announced that it had reached agreement on a repayment plan with the project's creditors, including Related Midwest, which had bought up much of the project's debt. Assuming the project finds funding to satisfy that agreement, Atlas said that the building would be built and that Atlas would control the project, but that Kelleher would still be the developer, with the intention of building the same building planned prior to the suspension of construction.[48]
In early 2018, the former developer Garrett Kelleher launched a $1.2 billion (USD) lawsuit, in the US Federal District Court in Illinois, against NAMA alleging that the agency destroyed his chances of building the Chicago Spire through a combination of "sheer spite" and "consistent incompetence". The lawsuit is formally brought by Kelleher's company, Shelbourne North Water Street Corporation.[49]
In 2016, Crain's Chicago Business reported that Related Midwest had hired former SOM architect Michael Pfeffer to guide the design of developments on the former Chicago Spire site. Although President Curt Bailey disclosed no project details—such as whether, for example, Related Midwest plans to build one big tower or multiple structures on the site—he did announce the development firm's intent to discuss plan outlines with the public in 2017.[50]
In 2018, it was revealed that Related Midwest will build two skyscrapers at the site of the Spire. The taller of the two would include 300 condominiums and a 175-room luxury hotel and the other 550 apartments.[51] The two tower plan has been approved by the city and the development will be called 400 Lake Shore Drive.[52]
Location
The skyscraper was being constructed at 400 N. Lake Shore Drive, on Chicago's waterfront west of Navy Pier and northeast of the Loop, in the Streeterville neighborhood of the Near North Sidecommunity area. The site is at the junction of Lake Michigan and the Chicago River, and is bordered by the Ogden Slip of the Chicago River to the north, North Lake Shore Drive to the east, the Chicago River to the south, and existing residential property to the west. The site was originally zoned for two 35 to 50-story buildings.[11] Originally, it was to be sold by a joint venture of LR Development Company of Chicago and JER Partners of Virginia for $64 million to Christopher Carley of the Fordham Company.[53] After numerous short-term extensions, and later Carley's failure to obtain financing, Kelleher of Shelbourne Development purchased the land instead and pledged to finance the rest of the project.[16]
When the project was first announced, the Fordham Company pledged almost $500,000 to assist in the development of the city's proposed DuSable Park, which would adjoin the property of the Chicago Spire.[54] DuSable Park would cover 3.24 acres (1.31 ha) and a $11.4 million budget was planned for its renovation.[55] On March 26, 2007, Shelbourne pledged to pay $6 million toward the development of the park, making up the deficit left over from the city's own initial pledge of $6 million and far exceeding the Fordham Co's initial offer.[56] In May 2007 Shelbourne's pledge jumped to $9.6 million.[57] Soil tests performed in December 2000 on the soil of the proposed park showed contamination of radioactivethorium.[58] Thorium was used by the Lindsay Light Company, which operated a location nearby. After the closing of the location in the 1930s, contaminated soil was dumped on the location of the proposed park. In March 2003, the Chicago Park District stated that the thorium clean-up on that land was incomplete.[59] Hazards of contamination can be avoided by laying a minimum of 6 inches (15 cm) of concrete over any affected soil, an approach that would be more feasible for the site of the Chicago Spire than for the adjacent park.[58]
In 2012 the Chicago Park District received funding from the EPA for remediation of the site, bagging the radioactive soil and shipping it to a Superfund site.[60] By summer 2013 the Park District website reported the remediation had been completed by September 2012.[61]
Architecture
As with many of his designs, Calatrava was inspired by themes and designs in nature for the tall, twisting skyscraper.[62] He likened the structure to an imaginary smoke spiral coming from a campfire near the Chicago River lit by Native Americans indigenous to the area,[63] and also related the building's newly designed pinnacle to the "graceful" and "rotating forms" of a snail shell.[21]
Standing at 2,000 feet (610 m), the Chicago Spire would have further transformed the always-growing Chicago skyline.[1][2][64] Plans for the tower included 1,193 condominiums with each of the building's 150 stories rotated 2.4 degrees from the one below it for a total 360-degree rotation.[65] In February 2008, prices for the condominiums were announced as ranging from $750,000 to US$40 million.[66] For supplemental structural support, each floor was to be surrounded by cantilevered corners and four concave sides.[67] Similar to the Willis Tower (formerly Sears Tower) and John Hancock Center observation decks, the Chicago Spire design included a community room on the top floor offering residents a view of four U.S. states.[68][69][70] The design for the soaring four story lobby of the skyscraper included translucent glass walls framed by arching, steel-reinforced concrete vaults.[21] The building has been described as a giant "drill bit" by the public and others in the media have likened it to a "tall twisting tree" and a "blade of grass".[19][71]
The curved design offered two major benefits to the structure of the building. First, curved designs, such as that found in Calatrava's Turning Torso in Malmö, Sweden, tend to add to the strength of a structure.[72] A similar principle has been used in the past with curved stadium roofs. In addition to structural support, the curved face of the exterior would minimize wind forces. In rectangular buildings, a fluid wind flow puts pressure on the windward face of the building; while air moves around it, a suction is applied to the leeward face. This often causes a sway in tall buildings usually counteracted, at least partially, by stiffening the structure or by using a dynamic wind damper.[72] Since the curved design of the Chicago Spire would not completely negate wind forces, a tapering concrete core and twelve shear walls radiating from it were planned to counteract the remaining wind load.[67]
Additionally, the Chicago Spire was designed with world-class sustainable engineering practices to meet Leadership in Energy and Environmental Design Gold recognition. Sustainable features included recycled rainwater, river water used for cooling, ornithologically-sensitive glass to protect migratory birds, intelligent building and management systems, waste storage and recycling management, and monitored outdoor air delivery.[65]
Construction
Following the city approval, it was announced that construction of the Chicago Spire was to begin in the summer of 2007, with caisson work scheduled to begin as early as June 2007.[73] DuSable Park was designated as a staging area for the construction of the tower.[74] The sales center for the Chicago Spire opened on January 14, 2008.[75]
On September 19, 2008, a spokeswoman for the developer announced that construction was continuing on the building, but that the pace of construction would be slowed until the financial markets recovered from the subprime mortgage crisis.[76] Kelleher promised that he still had financial backing,[76] although analysts questioned the ability of the project to survive the current economic decline.[77] A contractor to build the building's superstructure had not yet been named.[77] The October 1, 2008 edition of The Wall Street Journal said that the building foundation was complete and the above ground construction would not continue until the markets recover.[78] The Spire has remained a fenced-off hole in the ground at 400 N. Lake Shore Drive since 2008. But before Shelbourne faced financial difficulties and was forced into bankruptcy, about 370 of the planned 1,200 luxury condos were sold, half of which were to people outside the U.S., according to the suit.
“Shelbourne remains the only person logically capable of completing it because it still owns the intellectual property necessary to construct it and it still maintains the goodwill of the diverse governmental and community interests without which a project of this dimension would be doomed,” the lawsuit states.
Underground phase
Crane parts and construction equipment arrived at the site on June 25, 2007.[79] The following day Shelbourne Development officially announced the first construction contract.[5] In preparation for construction, 34 concrete and steel caissons were drilled 120 feet (37 m) into bedrock underground; this was completed June 25, 2008.[5] A cofferdam with a 104 foot (32 m) diameter and 78 foot (24 m) depth was installed to create a work environment and would have later acted as a foundation for the building's core.[5] Utility upgrades were planned for the surrounding neighborhood.[80]
^Herrmann, Andrew (September 18, 2006). "A DuSable park at last". Chicago Sun-Times. Archived from the original on October 13, 2007. Retrieved July 19, 2009.
Keegan, E. (2005). Calatrava designing massive tower in Chicago. Architectural Record, 193, 29.
McKeoug, T. (2006). Artist at work: Santiago Calatrava. Azure, 22, 56–61.
Nobel, P. (2005). Onward and upward? Four years after 9/11 – at perhaps the peak of the real estate bubble – very tall has never been hotter. Metropolis, 25, 66–72.
Pridmore, J., & Larson, G.A. (2005) Chicago Architecture and Design : Revised and expanded. Harry N. Abrams, Inc.: New York.
External links
Wikimedia Commons has media related to Chicago Spire.
Antigua dan BarbudaJulukanBenna BoysAsosiasiAsosiasi Sepak Bola Antigua dan BarbudaKonfederasiCONCACAF (Amerika Utara, Tengah, dan Karibia)Sub-konfederasiCFU (Karibia)PelatihTom Curtis[1]KaptenQuinton GriffithPenampilan terbanyakPeter Byers (93)Pencetak gol terbanyakDerrick Edwards (59)Stadion kandangStadion Sir Vivian RichardsAntigua Recreation GroundKode FIFAATGPeringkat FIFATerkini 139 2 (26 Oktober 2023)[2]Tertinggi83 (November 2011)Terendah170 (Desember 2003)Peringkat Elo...
Church in Edinburgh, Scotland This article needs additional citations for verification. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.Find sources: Augustine United Church – news · newspapers · books · scholar · JSTOR (May 2014) (Learn how and when to remove this template message) ChurchAugustine United Church55°56′51.3″N 3°11′29″W / 55.947583°N 3.19...
Glacier of Graham Land, Antarctica Location of Aristotle Mountains on the Antarctic Peninsula. Stubb Glacier (65°41′S 62°10′W / 65.683°S 62.167°W / -65.683; -62.167) is 11 nautical miles (20 km) long in Aristotle Mountains on the east coast of Graham Land, flowing east from Mount Sara Teodora into Scar Inlet between Mount Queequeg and Tashtego Point. The lower reaches of this glacier were surveyed and photographed by the Falkland Islands Dependencies Surve...
Pour les articles homonymes, voir Certification. Certificat électronique client-serveur de comifuro.net Un certificat électronique (aussi appelé certificat numérique ou certificat de clé publique) peut être vu comme une carte d'identité numérique. Il est utilisé principalement pour identifier et authentifier une personne physique ou morale, mais aussi pour chiffrer des échanges[1]. Il est signé par un tiers de confiance qui atteste du lien entre l'identité physique et l'entité nu...
سان مارتينو سولا ماروتشينا شعار الإحداثيات 42°13′30″N 14°12′52″E / 42.224991666667°N 14.214311111111°E / 42.224991666667; 14.214311111111 [1] تقسيم إداري البلد إيطاليا[2] التقسيم الأعلى مقاطعة كييتي خصائص جغرافية المساحة 7.41 كيلومتر مربع (9 أكتوبر 2011)[3] ارتفا...
كلب بلديملصق الفيلممعلومات عامةالصنف الفني كوميديتاريخ الصدور مصر 8 سبتمبر 2016مدة العرض 100 دقيقةاللغة الأصلية اللغة العربيةالبلد مصرموقع التصوير مصرالطاقمالمخرج معتز التونيالكاتب أحمد فهميشريف نجيبالبطولة دينا محسن (ويزو)بيومي فؤادحمدي الميرغنيأحمد فهميأحمد ف
Flagge von Osttimor Die Lage Osttimors Geschichte Osttimors (Osttimor) Alieu Ainaro Baucau Maliana Suai Dili Gleno Lospalos Liquiçá Manatuto Same Pante Macassar Viqueque Tatamailau Indonesien Indonesien Timorsee Sawusee Bandasee Atauro Jaco Die Geschichte Osttimors umfasst die Entwicklungen auf dem Gebiet der Demokratischen Republik Timor-Leste von der Urgeschichte bis zur Gegenwart. Sie ist geprägt von einer langen Zeit der Fremdherrschaft. 450 Jahre beherrschten die Portugiesen den Osten...
Cricket stadium This article's tone or style may not reflect the encyclopedic tone used on Wikipedia. See Wikipedia's guide to writing better articles for suggestions. (October 2021) (Learn how and when to remove this template message) Shaheed Veer Narayan Singh International Cricket Stadium, RaipurStadium view from standGround informationLocationSector-3 Nava Raipur, Raipur,Chhattisgarh,IndiaCoordinates21°12′15″N 81°49′24″E / 21.20417°N 81.82333°E / 21.204...
Australian cricket tournament 1958–59 Sheffield Shield seasonCricket formatFirst-classTournament format(s)Double round-robinChampionsNew South Wales (31st title)Participants5Matches20← 1957–581959–60 → The 1958–59 Sheffield Shield season was the 57th season of the Sheffield Shield, the domestic first-class cricket competition of Australia. New South Wales won the championship for the sixth consecutive year.[1][2] Table Team Played Won 1st Inns Won 1st Inns ...
Royal Canadian Air Force Command Chief Warrant OfficerRank insigniaIncumbentCWO John Hallsince June 10, 2021 The Royal Canadian Air Force Command Chief Warrant Officer is the senior non-commissioned officer in the Royal Canadian Air Force. They act as an advisor to the Commander of the RCAF on matters affecting all ranks in matters related to dress, discipline, morale and welfare, and quality of life. Specifically, they are responsible for: Understanding the issues that personnel face th...
American basketball player (1941–2016) Nate ThurmondThurmond with the Warriors in 1969Personal informationBorn(1941-07-25)July 25, 1941Akron, Ohio, U.S.DiedJuly 16, 2016(2016-07-16) (aged 74)San Francisco, California, U.S.Listed height6 ft 11 in (2.11 m)Listed weight225 lb (102 kg)Career informationHigh schoolCentral (Akron, Ohio)CollegeBowling Green (1960–1963)NBA draft1963: 1st round, 3rd overall pickSelected by the San Francisco WarriorsPlaying career1963...
SEMI-RETIRED This user is no longer very active on Wikipedia. This is a Wikipedia user talk page.This is not an encyclopedia article or the talk page for an encyclopedia article. If you find this page on any site other than Wikipedia, you are viewing a mirror site. Be aware that the page may be outdated and that the user whom this page is about may have no personal affiliation with any site other than Wikipedia. The original talk page is located at https://en.wikipedia.org/wiki/User_talk:Emme...
American PBS children's programming brand PBS KidsNetworkPBSLaunchedJuly 11, 1994; 29 years ago (1994-07-11) (PTV)September 6, 1999; 24 years ago (1999-09-06) (as PBS Kids)Country of originUnited StatesFormerly known asPTV (1994–99)Official websitepbskids.org PBS Kids (stylized as PBS KIDS) is the brand for most[note 1] of the children's programming aired by the Public Broadcasting Service (PBS) in the United States. The target audience is childre...
Comic book Superman versus The Terminator: Death to the FutureCover of Superman versus The Terminator: Death to the Future #1 (December 1999).Publication informationPublisherDark Horse Comics DC ComicsScheduleMonthlyFormatLimited seriesGenreSuperhero fictionScience fantasyPublication dateDecember 1999 - March 2000No. of issues4Main character(s)SupermanTerminatorCreative teamWritten byAlan GrantPenciller(s)Steve PughInker(s)Mike PerkinsLetterer(s)Clem RobinsColorist(s)Dave StewartCollected edi...
Cricket stadium in Bangalore city, Karnataka, India This article needs additional citations for verification. Please help improve this article by adding citations to reliable sources. Unsourced material may be challenged and removed.Find sources: M. Chinnaswamy Stadium – news · newspapers · books · scholar · JSTOR (October 2012) (Learn how and when to remove this template message) M. Chinnaswamy StadiumInside view of the stadiumGround informationLocati...
Casino in Scarborough, North Yorkshire, England Opera House CasinoOpera House Casino, Scarborough Location Scarborough,North Yorkshire,England Address 56-64 St Thomas Street, Scarborough, North Yorkshire. YO11 1DUOpening date26 October 2005ThemeEuropean StyleOwnerNikolas ShawArchitectFrame InternationalCoordinates54°17′03″N 0°24′02″W / 54.28414°N 0.400455°W / 54.28414; -0.400455Websitehttp://www.operahousecasino.co.ukThe Opera House Casino is a casino locat...
عدم المساواة التعليمية هو التوزيع غير المتكافئ للموارد الأكاديمية في المجتمعات المستبعدة أو المهمشة اجتماعياً؛ ليشمل على سبيل المثال توافر التالي: تمويل المدارس ومعلمين أكفاء وذوي الخبرة وكتب دراسية وأساليب تكنولوجية متقدمة. تاريخياً تعاني المجتمعات المهمشة من الحرمان...
Indoor arena in Moscow, Russia Luzhniki Small Sports ArenaFormer namesMinor Arena of the Central Lenin StadiumLocationKhamovniki District, Moscow, RussiaCoordinates55°43′06″N 37°32′56″E / 55.71833°N 37.54889°E / 55.71833; 37.54889Capacity8,700Opened1956TenantsDynamo Moscow (2000–2015)Websitewww.luzhniki.ru The Luzhniki Small Sports Arena (formerly, the Minor Arena of the Central Lenin Stadium; Russian: Малая спортивная арена Лужни...
Charles M. SchulzCharles M. Schulz pada tahun 1956, menggambar Charlie BrownNama lahirCharles Monroe SchulzLahir26 November 1922 (umur 101)Minneapolis, Minnesota, Amerika SerikatMeninggal12 Februari 2000(2000-02-12) (umur 77)Santa Rosa, California, Amerika SerikatDinas/cabangAngkatan Darat Amerika SerikatLama dinas1943-1946PangkatSersan StafKesatuan Divisi Lapis Baja ke-20Perang/pertempuranPerang Dunia IIPenghargaan Combat Infantryman Badge Wo...
Corps of the French Army, which is partly made up of foreign nationals Legionnaire redirects here. For other uses, see Legionnaire (disambiguation). Foreign LegionLégion étrangèreThe Foreign Legion's grenade emblemActive10 March 1831 – presentCountry FranceBranch French ArmyTypeAssault troops Foreign legionRoleLand warfareExpeditionary warfareAirborne forcesSize9,000 SoldiersNickname(s)La LégionThe LegionPatronSaint Anthony[1]Motto(s)Honneur et FidélitéLegio Patria Nostra...
Strategi Solo vs Squad di Free Fire: Cara Menang Mudah!