The project was announced and laid down by the then Chief Minister of Uttar PradeshAkhilesh Yadav as Lucknow-Azamgarh-Ballia Samajwadi Purvanchal Expressway in May 2015.[7][8] Later, route was changed to Lucknow-Azamgarh-Ghazipur by the Yogi Adityanath government, and upon acquisition of around 95% of required land, foundation stone of Purvanchal Expressway was laid on 14 July 2018 by Prime Minister Narendra Modi.[9][10][11][12][13][14] With a total project value of ₹22,494 crore, including the land acquisition cost, the Expressway was India's longest expressway at the time of completion.[15][16]
5 industrial corridors will be set up alongside Purvanchal Expressway. As on Nov., 2023, the land has been identified and process for bainama is underway. In Ghazipur district, 25% bainama of land has been done till May, 2024.
The UPEIDA divided the construction work of 340.8 km long Purvanchal Expressway into 8 packages, which were awarded to 5 different contractors.[20] The design work was done by Egis India Consulting Engineers (Package 1 to 4) and Ayesa India (Package 5 to 8).
22 Flyovers, 7 Railway-over-bridges (ROB), 7 major bridges, 114 minor bridges, 6 Toll Plazas, 45 vehicular-underpasses (VUP), 139 Light VUP, 87 pedestrian underpass and 525 Box culverts has been constructed.[21] Total construction cost (excluding the cost of Land) is around ₹11,216 crores.
Prime Minister Narendra Modi arrived at the inauguration site in the C-130 Hercules and later touch and go exercise was also performed on the expressway by the Indian Air Force (IAF).[24][25] Indian Air Force fighter jets performed the 'touch and go' operation, under which 30 fighter planes touched the Purvanchal expressway airstrip and then took off. Fighter jets including Mirage 2000, AN-32, Jaguar, and Sukhoi performed touch and go operations and showcased a landing on the expressway. The Indian aircraft showcased tricolor in the sky.[26]
May 2015: Uttar Pradesh Chief Minister Akhilesh Yadav announces intention to take up the Lucknow-Ballia Expressway soon.[31]
Oct 2015: Government of UP finalized the alignment out of three proposed alignment for expressway. Detailed Project Report (DPR) to be prepared in three months.[32]
Nov 2015: The Lucknow–Azamgarh–Ballia Expressway renamed as Purvanchal Expressway.[33]
Feb 2016: State Government allocated ₹1,500 crores for the expressway in the budget.[34]
Dec 2016:Akhilesh Yadav, then Chief Minister of Uttar Pradesh lays foundation stone of Lucknow-Azamgarh-Ballia Expressway on 22 December 2016.[35][36][37][38][39]
Mar 2017:Yogi Adityanath of BJP became the new Chief Minister of Uttar Pradesh on 19 March 2017.
May 2017:Yogi Adityanath government cancels tenders issued by the previous Akhilesh Yadav government, stating that currently only 40.17% of needed land is acquired. The fresh tenders will be issued, when at least 80% of the required land will be acquired.[40] UP Government orders faster land acquisition.[41]
Sep 2017: 60% land acquired at cost of ₹4,500 crore. Total land acquisition may cost up to ₹6,500 crore. NITI Aayog says the Central Government may bear construction cost, if UP government bears the land acquisition cost.[42]
Jan 2018: 85% land acquisition done, foundation stone to be laid in March 2018.[43]
Jun 2019:Government of Uttar Pradesh saves ₹620 crore in bidding process for Purvanchal Expressway.[47] 10% of construction work has been completed.
Jul 2019: Proposal to extend the Purvanchal Expressway to Ballia.[48]
Sep 2019: 97% of earth work completed. To check the progress of construction work without physical inspection, UPEIDA to launch mobile app soon.[49]
Oct 2019: 20% of construction work is completed.[50]
Apr 2020: Work resumed after being on-hold for nearly a month due to COVID-19.[51]
Aug 2020: 52% of construction work completed, as of 10 August.[52]
Jun 2021: 90% of construction work and 928 out of total 934 structures completed as of 28 June.[53]
Jul 2021: 95% of construction work and 930 out of total 934 structures completed as of 26 July. The deadline for construction work is October 2021.[54]
Sep 2021: On 10 September, CM Yogi Adityanath confirmed to inaugurate the expressway in October 2021.[55] 97% of construction work completed as of 20 September.[56]
May 2022: Toll collection starts at all Toll Plazas with effect from 1 May 2022.
Controversies and Criticism
The first seasonal rains in October 2022 caused wide stretches of road caving deep in, some extending to even 15 feet deep. Accidents were reported at several places, with multiple injuries and damage to numerous cars garnering significant coverage in media. The much proclaimed dream project of Yogi Adityanath, built over a whopping 22000 crore expense by the Yogi government and inaugurated by Prime Minister Narendra Modi in November 2021, faced subsequent backlash and criticism for the alleged irregularities and corruption in construction of the expressway which couldn't withstand the first few hours of rain within a year following its inauguration.[59][60][61][62][63][64][65][66]