The Crescent Dunes Solar Energy Project is a solar thermal power project with an installed capacity of 110 megawatt (MW)[4] and 1.1 gigawatt-hours of energy storage[1] located near Tonopah, about 190 miles (310 km) northwest of Las Vegas.[5][6]
Crescent Dunes is the first commercial concentrated solar power (CSP) plant with a central receiver tower and advanced molten salt energy storage technology at full scale (110 MW), following the experimental Solar Two and Gemasolar in Spain at 50 MW. As of 2023, it is operated by its new owner; ACS, and in a new contract with NV Energy, it now supplies solar energy at night only, drawing on thermal energy stored each day.[7]
Startup energy venture company SolarReserve (created via seed funding), US Renewables Group, and United Technologies were the original owners of Tonopah Solar Energy LLC, the owner and operator of the Crescent Dunes plant. The Crescent Dunes project was subsequently backed by a $737 million in U.S. government loan guarantees and by Tonopah partnering with Cobra Thermosolar Plants, Inc. The overall venture had a projected cost of less than $1 billion.[8][9]
The plant suffered several design, construction and technical problems and, having not produced power since April 2019, its sole customer, NV Energy, subsequently terminated its contract. Bloomberg reported that NV Energy was not allowed to sever its agreement with the plant until after the DoE took over the shuttered plant in August 2019.[10][11]
Since the initial failure of the Crescent Dunes project, SolarReserve took down its website and is believed to have permanently ceased operations.[12][13] Upon the developer's silence as the involved parties sought legal recourse, the plant's exact status was publicly unknown for some time and was left to conjecture.[14][15][16]
While proceeding through its subsequent bankruptcy proceedings, Tonopah Solar Energy stated that it had hopes for a restart of the Crescent Dunes plant by the end of 2020.[17][18] According to court documents, Tonopah is owned by SolarReserve, Cobra Energy Investment LLC, a division of Spanish construction company ACS Group and Banco Santander, S.A.[19] On September 11, 2020, the bankruptcy court approved Tonopah Solar Energy's disclosure statement. On December 3, 2020, the Chapter 11 bankruptcy reorganization plan was confirmed by the court.[20] As one result of this plan's confirmation, Cobra now has operational control of the plant.[18] In July 2021, the project restarted production for NV Energy.[21]
History
In late September 2011 Tonopah Solar Energy received a $737 million loan guarantee from the United States Department of Energy (DOE) and [5] the right to build on public land.[22] The capital stack included $170,000,000 in EB-5 investment through SolarReserve/ACS Cobra partner CMB Regional Centers.[23][24][16]
Under a power purchase agreement (PPA) between SolarReserve and NV Energy, all power generated by the Crescent Dunes project in the next 25 years would have been sold to NV Energy for $0.135 per kilowatt-hour.[9]
Ground was broken on the project in September 2011.[25]
Construction terminated at the end of 2013, followed by several months of testing the plant systems. The project entered commissioning phase in February 2014 following completion of construction.[26]
It began operation in September 2015,[27] but went off-line in October 2016 due to a leak in a molten salt tank. The owners warned the EPC about flaws in the salt tank foundations (and other matters) with formal comments lodged on the record in March 2012 progress meeting with DOE and its engineer present (the lender did not voice any objection).
It returned to operation in July 2017.[28]
The plant having last produced power in April 2019, NV Energyโthe project's sole customerโterminated its contract in October 2019 on the basis of the project having "failed to produce." Alleging a takeover of Tonopah Solar Energy by the DOE,[11] SolarReserve then raised the possibility of the project filing for bankruptcy, which subsequently happened.[29][30] SolarReserve also filed a lawsuit, claiming that the Department of Energy was looking to appoint two new members to Tonopah Solar Energy's board of managers, giving the appearance of the Energy Department in complete control of Tonopah directors which comprise the entirety of the Tonopah Board of Managers.[11] An interim outcome in this regard was that SolarReserve took down its website and was believed to have ceased operations permanently.[13]
Tonopah Solar Energy filed for bankruptcy on July 30, 2020.[19] Pending the approval of the bankruptcy court, a $200 million settlement with the remaining debtors โ Tonopah Solar Energy LLC and ACS Cobra โ for the return of taxpayer dollars was also announced at the end of July 2020.[31] The amount is less than half of what taxpayers are owed on the outstanding $425 million of public debt.[32] Under the settlement agreement and as a function of subsequent repairs, restoration of the plant to power production and acquisition of new long-term customers, ACS Cobra is liable for an additional $100 million in otherwise suspended debt.[33]
Technology
The project's EPC Contractor was ACS Cobra, which carried out the engineering design, procured the equipment and materials necessary, and then constructed and delivered the facility to Tonopah Solar Energy. The project includes 10,347 heliostats that collect and focus the sun's thermal energy to heat molten salt flowing through an approximately 656-foot (200 m) tall[13]solar power tower. Each heliostat is made up of 35 6ร6 feet (1.8 m) mirror facets, yielding a heliostat overall usable area of 1,245 square feet (115.7 m2). Total solar field aperture adds up to 12,882,015 square feet (1,196,778 m2). The molten salt circulates from the tower to a storage tank, where it is then used to produce steam and generate electricity.
Excess thermal energy is stored in the molten salt and could be used to generate power for up to ten hours, including during the evening hours and when direct sunlight is not available.[5] The storage technology thus eliminated the need for any backup fossil fuels, such as natural gas. Melting about 70,000,000 pounds (32,000,000 kg) of salt took two months. Once melted, the salt stays melted for the life of the plant and is cycled through the receiver for reheating.[34]
The thermal storage high-temperature salt tank buckling failure
Crescent Dunes was the first large (110 MW) tower CSP with thermal storage. While storage tanks of trough CSP operate at 400 ยฐC (752 ยฐF), Crescent Dunes operated the storage tank at almost 600 ยฐC (1,112 ยฐF), while keeping 280 ยฐC (536 ยฐF) as base (cold) temperature.
Higher temperatures differences result in a greater expansion of the tank floor, generating greater compressive forces around the floor plate. At very large diameters, as the big tank of Crescent Dunes, that resulted in a high probability of failure under cycling loading.[35]
Production
Crescent Dunes began operation in September 2015,[27] but went off-line in October 2016 due to a leak in a molten salt tank. It returned to operation in July 2017.[28] While its average monthly production was expected to exceed 40,000 MWh, as of May 2019 it never reached that value and only exceeded half of it during 9 months.[36]
Generation (MWยทh) of Crescent Dunes Solar Energy[37]
Year
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Total
2015
1,703
1,831
0
3,534
2016
1,508
9,121
7,099
2,158
11,485
6,216
25,560
28,267
30,514
5,410
0
0
127,338
2017
0
0
0
0
0
0
9,420
9,192
13,666
9,263
488
0
42,029
2018
795
5,145
5,907
13,801
10,653
33,387
23,749
33,169
31,632
21,253
8,130
8,189
195,810
2019
12,889
14,431
20,041
2,807
Production suspended
50,168
2020
Production suspended
0
2021
Production suspended
3,974
15,445
20,796
11,929
17,489
5,088
74,721
2022
14,635
12,238
0
0
0
0
0
8,852
22,166
24,710
10,590
7,475
100,666
2023
8,437
2,086
0
0
0
0
6,649
14,563
13,784
18,060
10,590
6,067
80,236
2024
4,556
4,122
6,448
13,516
20,968
26,227
-
-
-
-
-
-
-
The commissioning of a new thermal plant requires up to four years to achieve 100% operating level, from the first grid connection to full production. As an example the Edwardsport production data, whose progression, skipping first partial year, is a 40% output the first full year, 57% the second full year, the next year the progression was stopped by a problem in October, but resumes with a 73% the fourth and next year.[38] At Crescent Dunes, it was to be expected a similar progression, but the failure of the storage tanks in 2016, froze the commissioning.[39] Following that, first full production year was delayed to 2018, starting with a 40% (200 over 500) output.
Shutdown
The first three months of 2019 (January, February and March) showed good progression, topping all previous monthly data, but in April the plant was shut down because the project's sole buyer, NV Energy, terminated the Power Purchase Agreement for failure to produce the contracted power production. The power generated also cost NV Energy about $135 per megawatt-hour, compared with less than $30 per MWh available from a new Nevada photovoltaic solar farm.[40][16] But to compare fairly, it must be taken into account that the Tonopah solar project power is dispatchable while photovoltaic power is intermittent. Truly levelized cost comparisons must include the capacity payments for generating capacity available to supply power during peak hours. By doing so, low-to-high hourly wholesale electricity prices have been shown to vary by up to four orders of magnitude.[41][42]
In July 2021, the project restarted production.[21]
Gallery
2012 January โ The solar tower under construction as seen from a commercial airliner. The eponymous Crescent Dunes are at lower right.
2014 December โ Completed site as seen from a commercial airliner.
2024 August - Crescent Dunes Solar Energy Project as seen from commercial airliner
^Delbert, Caroline (January 10, 2020). "The $1 Billion Solar Plant Is an Obsolete, Expensive Flop". www.popularmechanics.com. Hearst Digital Media. Archived from the original on January 21, 2021. Retrieved January 27, 2022. Bloomberg reports that even though the plant shut down in April 2019, NV Energy was not allowed to sever its agreement with the plant until late in 2019, after the DoE was forced to take over the shuttered plant in August. SolarReserve took the DoE to court.
^ abcSchulz, Bailey (October 7, 2019). Cook, Glenn (ed.). "Tonopah solar plant could end up in bankruptcy, developer says". www.reviewjournal.com. Las Vegas: J. Keith Moyer. Archived from the original on October 8, 2019. Retrieved February 26, 2020. ... major decisions โ such as bankruptcy proceedings โ require a unanimous vote from the managers, the lawsuit alleges that the Energy Department can determine the fate of Tonopah Solar Energy without any representation of SolarReserve on the board
^Chris Martin; Nic Querolo (January 6, 2020). "A $1 Billion Solar Plant Was Obsolete Before It Ever Went Online". Bloomberg. Retrieved February 5, 2020. Harry Reid, then the Senate majority leader and senior senator from Nevada, cleared the way for the company to build on public land