Construction of the station began in March 2017,[3] a few months after the completion of the Gormley GO Station, which opened in December 2016.[2] The station site cost an estimated $82.4 million to develop[3] (the final cost was unconfirmed publicly), and the multi-level parking structure and integrated station building was built to satisfy LEED Gold certification.[5]
As of September 2021[update], Bloomington GO is served by four round trips per weekday; all Toronto-bound during the morning and returning northbound during the afternoon. Additional weekday service to Toronto is provided by the 61 GO bus.[9]