The Teesside Steelworks was a large steelworks that formed a continuous stretch along the south bank of the River Tees from the towns of Middlesbrough to Redcar in North Yorkshire, England. At its height there were 91 blast furnaces within a 10-mile radius of the area. By the end of the 1970s there was only one left on Teesside. Opened in 1979 and located near the mouth of the River Tees, the Redcar blast furnace was the second largest in Europe.[1]
The majority of the steelworks, including the Redcar blast furnace, Redcar and South Bank coke ovens and the BOS plant at Lackenby closed in 2015. The Teesside Beam Mill and some support services still operate at the Lackenby part of the site.
On 1 October 2022, the Basic Oxygen Steelmaking (BOS) Plant at Lackenby was demolished in one of the largest single explosive demolition operations in the country in 75 years.[2]
The firm later acquired the Southbank Steelworks and adopted the Gilchrist–Thomas process at the suggestion of its developer, Sidney Gilchrist Thomas. This allowed the use of local ironstone which had a high phosphorus content. Bolckow, Vaughan & Co Ltd were already well established producers of Iron owning many Ironworks and furnaces and were seen as the driving force behind the rapid expansion of Middlesbrough or "Ironopolis" and Great Britain's leading producer of pig iron.[7] After the company's acquisition of the Clay Lane works at the end of the century and a shift in production from Iron to steel they became the largest producers of steel in Great Britain and possibly the world, owning 21 of the 91 blast furnaces in the Cleveland area.[8][9]
In 1876, Arthur Dorman entered into a partnership with Albert de Lande Long to form Dorman Long, taking over the West Marsh Ironworks in Middlesbrough. Over next 10 years Dorman Long would expand further, acquiring the Brittania works in Middlesbrough,[10] and building a new steel works at the Clarence works in a joint venture with Bell Brothers.[citation needed]
Other developments
The amount of slag coming out of the various furnaces of Teesside increased substantially and its disposal became a costly problem for works' owners. One solution, invented in the 1870s, was the Scoria brick which became a major export of the region and can still widely be seen as a road surface in the local area.[11]
20th century expansion
This section needs expansion. You can help by adding to it. (August 2023)
In 1902, Dorman Long would build the first integrated steelworks at Cargo Fleet.[12] In the following year, Lowthian Bell, then aged 87, sold a majority holding of the Bell companies to the rivals Dorman Long.[13]
During the First World War Dorman Long was one of the first non-munitions company in Britain to dedicate itself to shell production.[14] By 1917, they had completed a new blast furnace at Redcar with a cost of £5.4 million. Some of the steel produced here, along with steel from the Brittania and Cargo Fleet steelworks, would be used to build notable structures including the Sydney Harbour Bridge, Tyne Bridge, in the 20s, and later, the Auckland Harbour Bridge.[15]
Interwar period
In 1923, Bolckow, Vaughan & Co acquired Redpath, Brown & Co, manufacturers of structural steel.[16]
As the 1920s went on Bolckow Vaughan found itself in an increasingly difficult financial situation. The works were reorganised, and consultation with the workforce introduced. The causes of these problems included: poor decision-making in the period from 1900–1910 which delayed the introduction of improved steelmaking technology; optimistic belief in promises of funding made by the British government during the war, leading to reliance on costly bank loans in 1918; and failure to invest in its own coal mines to provide enough for steel production, and for cash.[17][18][19] By 1929, the financial pressures, forced the company into a takeover by Dorman Long who by this point is also struggling financially.[20][21]
In 1946, The Lackenby development was built by Dorman Long between the Redcar and Cleveland Works.[citation needed]
In 1979, the new blast furnace opened at the former Redcar site using the open hearth process. It was the second largest of its kind in Europe and Teesside's sole remaining blast furnace, at that time.[22]
By 2003, Corus considered that the production at Teesside Cast Products (TCP) as a surplus to its needs.[24] Corus was bought by Tata Steel, in 2007.[25]
In 2009, Corus announced partial mothballing of the Teesside blast furnace. Approx. 1,700 jobs eliminated.[26][27] To help the workers, a Corus Response Group was formed which developed a comprehensive package of support. This plan was in place over the past 10 months of announcement and included employment experts on site from January 2010. Support was put in place to help affected workers with individual sessions to update CVs, highlight job opportunities and look at retraining options. The response group was also supposed to work with the Teesside Cast Products function to offer similar support.[28][29][30]
SSI
On 24 February 2011, the steelworks was purchased by Thai-based Sahaviriya Steel Industries (SSI) at $469 million.[31] The acquisition was expected to create more than 800 jobs on top of the existing workforce of 700 and the plant was officially reopened 15 April 2012.[27][32][33]
On 18 September 2015, production was paused due to the global decline in steel prices.[34]
On 28 September 2015, the plant was mothballed again amid poor steel trading conditions across the world and a drop in steel prices.[35]
On 2 October, SSI UK entered into liquidation.
On 12 October 2015, the receiver announced there was no realistic prospect of finding a buyer. The coke ovens were scheduled for extinguishing, however this time it was done without the complex decommissioning processes conducted in 2010, which would have allowed the facility to reopen in the future.[36]
British Steel
The remainder of the site is still operational (Teesside Beam Mill and ancillary support services at Lackenby and the deep-water bulk handling terminal), having been sold by Tata Steel to investment firm Greybull Capital on 1 June 2016. As part of the deal, the historic British Steel name was resurrected. The new company includes the UK sites at Skinningrove and Scunthorpe as well as the Hayange rail plant in northern France.[37][38]
Insolvency of British Steel
In May 2019 British Steel collapsed and was taken over by the Insolvency Service. It was later purchased in March 2020 by Jingye Group, who agreed to save the remaining jobs by modernising the steelworks.[39]
Electric Arc Furnace plans
In April 2024, British Steel won planning permission for an electric arc furnace to be built at the remaining Lackenby site. There is however no clear timetable for the actual construction of the structure.[40]
Demolition and Redevelopment
The steelworks' BOS plant, blast furnace, and power station, along with auxiliary structures, were demolished in between October 2022 and June 2023, creating a 4,500-acre site of brownfield land.[2][41][42]
The closure of the steelworks, coupled with the running down of many coal-fired power stations and a UK Government carbon tax, led to a 6% reduction in carbon emissions from the United Kingdom in 2016.[43]
Transport
The site is situated alongside the A66 and A1085 dual carriageways. Main access is via the Lackenby and Redcar entrances, situated on the A1085.
The site is adjacent to Teesport that was used for iron ore, coal, and other raw material imports, and steel exports.
The site was served by the Redcar British Steel railway station, which opened on 19 June 1978.[44]Northern discontinued service to the station in December 2019,[45] prior to this the station (owned by Network Rail), was surrounded by private land, which prevented any public access to or from the station.
^Abé, E. (1996). "The Technological Strategy of a Leading Iron and Steel Firm, Bolckow Vaughan & Co. Ltd: Late Victorian Industrialists Did Fail". Business History. 38: 45–76. doi:10.1080/00076799600000003.