Northern Lights Express

Northern Lights Express
Overview
Service typeInter-city, higher-speed rail
StatusPlanning
LocaleMinnesota and Wisconsin, United States
PredecessorArrowhead (1975–1978)
North Star (1978–1985)
First serviceTo be determined
Former operator(s)Amtrak
Annual ridership700,000 annually (projected)
Websitehttps://www.dot.state.mn.us/nlx/
Route
TerminiTarget Field Station, Minneapolis
Duluth Depot, Duluth
Stops6 (2 existing, 4 proposed)
Distance travelled152 miles (245 km)
Average journey time2.5 hours
Service frequencyFour daily round-trips
Technical
Track gauge4 ft 8+12 in (1,435 mm) standard gauge
Operating speed60 mph (97 km/h) (avg.)
90 mph (140 km/h) (top)
Track owner(s)BNSF, North Shore Scenic Railroad
Route map
Duluth Transportation Center
Duluth Depot
North Shore Scenic Railroad
Grassy Point Bridge
over the Saint Louis Bay
Superior
Kettle River High Bridge
over the Kettle River
Hinckley
Cambridge
Empire Builder and Northstar Line
Coon Rapids–Foley Boulevard
Empire Builder
Minneapolis Target Field
Metro Blue & Green lines

Handicapped/disabled access All stations are accessible

The Northern Lights Express (NLX) project is a planned higher-speed rail service that would run 155 miles (249 km) between Minneapolis and Duluth primarily in the U.S. state of Minnesota. A portion of the proposed line would run through neighboring Wisconsin to serve Duluth's "Twin Port" of Superior. Plans are to upgrade an existing BNSF Railway freight line to allow trains to travel at up to 90 miles per hour (145 km/h).[1][2] The train service would provide an alternative to travel along Interstate 35 corridor between Duluth and the Twin Cities.

The proposed service's trains would mostly follow the same route as Amtrak's former North Star, except originating in Minneapolis rather than Saint Paul, and would stop at a suburban station, Foley Boulevard. The proposed line follows part of Amtrak's Empire Builder and Metro Transit's Northstar Line.

History

The Northern Lights Express would be the first passenger rail service to Duluth since 1986, when Amtrak discontinued the 50-mile-per-hour (80 km/h) North Star.[1] Alternatives analysis and a corridor assessment report were complete as of mid-2010.[3] The line had initially been projected to open as early as 2012,[4][5][6] though more recent sources had stated 2013 or 2014 as start dates.[7] As of 2010, the project was entering either an 18-month environmental impact statement (EIS) process or a shorter environmental assessment (EA) review,[3] but it was unclear which path was to be taken. The shorter EA process was strongly advocated by former Rep. James Oberstar, former chairman of the U.S. House Transportation Committee, who represented northern Minnesota.[8]

In 1999, a Twin Cities commuter rail network was designated, overlaying was the tier two Bethel Corridor, running from a downtown Minneapolis station along the former North Star corridor to Cambridge. Another tier two commuter route, the Rush Line, would have connected Hinckley to downtown Saint Paul. In late 2009, Target Field Station was established as the new downtown Minneapolis train station with the first commuter service, the Northstar Line, mostly following the existing Empire Builder to Big Lake. A station at the expansive Foley Boulevard park & ride is considered an infill project for the Northstar Line.[9]

Discussion about the Northern Lights Express dates back at least a decade. A preliminary feasibility study was conducted around the year 2000, followed by a comprehensive feasibility study in 2006–2007.[4] A joint powers board was established in 2007 consisting of the regional rail authorities for counties along the corridor along with representatives from Minneapolis, Duluth, and the Mille Lacs Band of Ojibwe.[10] The name was given to the line in March 2008 by a vote of the corridor's stakeholders.[11]

A feasibility study was completed in late 2007 which evaluated service at speeds of 79 mph (127 km/h), 110 mph (177 km/h), and 125 mph (201 km/h), and service of eight round trips per day at 110 mph (177 km/h) was recommended. The 79 mph (127 km/h) option was discarded because it would not attract enough riders to cover operating costs. NLX supporters hope to receive funds from the Federal Railroad Administration which requires new train projects to show they will operate at a surplus each year, unlike the Federal Transit Administration that funded the Hiawatha and Northstar lines in the Twin Cities.[1] Trains would also operate at a surplus at 125 mph (201 km/h), but higher capital costs and only a modest reduction in travel time made that option look less attractive. The study used the diesel-powered Talgo XXI as a reference, which has poor acceleration above 110 mph (177 km/h).[12]

Planning for the line received a big boost at the end of September 2008 when U.S. Transportation Secretary Mary Peters announced that the federal government would contribute $30 million to passenger rail projects across the country. The contribution included $1.1 million for the Northern Lights Express.[13] On September 9, 2011, Transportation Secretary Ray LaHood announced a grant of $5 million to fund environmental and engineering studies for the project.[14] On March 18, 2013, the environmental assessment was completed and released on the Minnesota Department of Transportation (MnDOT) website.[15]

In 2015 a press conference revealed an updated look at the NLX plan. The train would operate at 90 mph (140 km/h) and use the Siemens Charger locomotive instead of the Talgo. This proposal included six stations served by four daily trains in each direction. Tier 2 studies of the line would continue until 2017. As of June 2019, the project had failed to secure funding.[16] However in February 2020, a proposal was made to grant $40 million in funding for the project.[17]

Early 2022 saw momentum to acquire funding for the line. As part of the proposed 2022 state bonding bill, Governor Tim Walz earmarked $16.1 million for safety, capacity, and infrastructure improvements in the corridor, and if passed would receive a federal match of $80 million. Supporters have pointed out that Northern Lights Express would be eligible for funds appointed to Amtrak–State projects under the Infrastructure Investment and Jobs Act, with Northern Lights Express able to receive priority as a shovel ready project.[18] Representatives Mary Murphy and Liz Olson co-sponsored two bills in the Minnesota House that would allocate $85 million for the project, activating the remaining $320 million from the Department of Transportation. Senator Jerry Newton announced they would sponsor companion bills in the Minnesota Senate.[19]

Following the 2022 MN state elections, the 93rd Minnesota Legislature approved $194.7 million dollars in state funding for the route.[20][21]

In December 2023, the Federal Railroad Administration accepted an application by MnDOT to enter the Minneapolis–Duluth route into its Corridor Identification and Development Program. The program grants $500,000 toward service planning and prioritizes the route for future federal funding.[22]

Required track improvements

The Northern Lights Express is planned to use several segments of BNSF track. Starting from the south, it would run along the Wayzata Subdivision from Target Field to Minneapolis Junction, the Midway Subdivision to Northtown Yard, and then enter the Staples Subdivision—the same as the current Northstar commuter line. The NLX would turn north at Coon Creek Junction in Coon Rapids to enter the Hinckley Subdivision, which it would follow to Boylston Junction between Foxboro and Superior, Wisconsin. From Boylston, the train would use BNSF's Lakes Subdivision to reach Superior. From Superior to Duluth, the train would be on BNSF again, crossing the Grassy Point swing bridge back into Minnesota and then turning northeast to travel along the shore of St. Louis Bay. The train would exit BNSF rails at Rice's Point and would then run along the North Shore Scenic Railroad for a short segment into the Duluth Union Depot.

A preliminary study from around the year 2000 projected a cost of $79 million to purchase rolling stock and upgrade track along the existing line, though this apparently only anticipated 79 miles per hour (127 km/h) service.[4] The cost projection grew to $320 million in 2008, and $615 million in 2009, with a "worst-case scenario" number of $990 million.[23][24] The latest budget as of 2017 is around $425 million. "Construction costs include final design work, track and signal upgrades to accommodate higher speeds, new and longer sidings to improve traffic flow, grade crossing improvements to increase safety, new train stations, and the expansion of existing stations."[25] Up to 80% of the cost may be covered by the federal government, only requiring 20% from state and local sources. This is comparable to highway projects which often receive 80% or 90% funding from the federal government,[26][27] and is in contrast to the Hiawatha light rail and Northstar commuter lines which received 50% matching federal funds.

The wide range of cost estimates relates to how much of the 140-mile (230 km) line between Coon Creek Junction and Duluth would need to be upgraded from the current single-track configuration to a double-track corridor. Running double track all the way to Duluth may bring the cost to $990 million, but the NLX organization has preferred to only run double track north to Sandstone. It was also considered key to upgrade the rails to let trains make the trip in two hours or less. At that pace, the trains could do more than one round trip per day, reducing the number of trainsets needed to provide frequent service. The NLX organization revisited some slower options in 2010, and is now leaning toward Option 2 that would mostly run at 90 mph (140 km/h) north of the Twin Cities, but would support speeds up to 110 mph (180 km/h) between Cambridge and Hinckley. This would significantly reduce the cost and lead to better benefit-cost calculations, but would also reduce the operating margin to barely better than break-even.[28][29] Option 2 would have trains take 2 hours and 17 minutes to make the trip, and drop the average speed from about 78 mph (126 km/h) to about 68 mph (109 km/h). This still compares favorably with the scheduled 3 hours 35 minutes scheduled for the North Star in 1985—a mere 43 mph (69 km/h) average.[30]

As of 2009, the line hosted 12 to 15 freight trains per day.[31] It had at least some Class 4 track[32] which limits freight to 50 mph (80 km/h) and passenger traffic to 79 mph (127 km/h), but this would need to be upgraded to Class 5 and Class 6 in order to support 90 and 110 mph (140 and 180 km/h) speeds, respectively.[12] There are more than 150 grade crossings and 12 bridges on this segment which would need to be improved (or eliminated, in the case of some grade crossings). The line has automatic block signaling, but needs centralized traffic control and positive train control installed to support speeds above 79 mph (127 km/h).[33] There are also several sidings along the route which only have manual switches and would need to be automated.[12]

The double-track main line south of Coon Creek Junction is the busiest rail corridor in the Twin Cities metropolitan area. In July 2009, before the Northstar commuter line began operation, this segment hosted 63 trains per day.[31] There are already plans for BNSF to construct a third main line in the area from the junction south to East Interstate (the bridge over Interstate 694). BNSF would then allow 22 more passenger trains per day for Northstar, NLX, Amtrak, and possibly other services.[34] The Northstar's Fridley station was built with the future third main in mind, and was initially built as an island platform with track only on the east side, requiring the Northstar train to be on that track when traveling inbound to or outbound from Minneapolis.

Stations list

Station City State Notes
Duluth Depot Duluth Minnesota
Superior Wisconsin
  • Superior bypassed by the North Star in 1984
Hinckley Minnesota
Cambridge
  • Station to be integrated into the Cambridge City Center Mall
  • Cambridge last served by the North Star in 1985
Foley Boulevard Coon Rapids
Target Field Station Minneapolis
Northern Lights Express (source)

References

  1. ^ a b c Bodley, Peter (January 22, 2008). "Passenger rail service gets green light from consultant". ABC Newspapers.
  2. ^ Hollingsworth, Jana (March 2, 2024). "Plans for speedy passenger train to Duluth have slow start". Star Tribune. Retrieved March 3, 2024.
  3. ^ a b SRF Consulting Group, Inc. (July 2010). "NLX Open House Boards" (PDF). Northern Lights Express. Retrieved September 22, 2010.
  4. ^ a b c Kelleher, Bob (December 12, 2006). "Duluth ponders commuter rail". Minnesota Public Radio.
  5. ^ Kelleher, Bob (February 22, 2008). "Another push for Duluth to Minneapolis rail service". Minnesota Public Radio.
  6. ^ "Proposed Passenger Train 'On Track'". KDLH-TV. February 20, 2008.
  7. ^ "Transportation Interchange" (PDF). Hennepin County. November 2009. Retrieved September 22, 2010.
  8. ^ "Meeting Minutes" (PDF). Minnesota Department of Transportation. April 6, 2009. Retrieved December 21, 2009.
  9. ^ "Minnesota Comprehensive Statewide Freight and Passenger Rail Plan" (PDF).
  10. ^ "History of the NLX". Northern Lights Express. Retrieved December 14, 2009.
  11. ^ "Proposed Minneapolis-Duluth Rail Line Given Name". WCCO-TV. March 14, 2008.
  12. ^ a b c Minneapolis–Duluth/Superior: Restoration of Intercity Passenger Rail Service Comprehensive Feasibility Study and Business Plan (ch. 1–2, ch 3, ch 4–10, appendices). Transportation Economics & Management Systems, Inc., December 2007. Accessed December 18, 2009.
  13. ^ "Duluth-Twin Cities Rail Line On Federal Money List". wcco.com. September 30, 2008.
  14. ^ "Minnesota's Northern Lights high speed rail project receives $5m grant". Rail.co. September 9, 2011. Archived from the original on March 20, 2012. Retrieved September 12, 2011.
  15. ^ "Northern Lights Express: Proposed passenger rail service between Minneapolis and Duluth, MN". April 9, 2013. Retrieved April 9, 2012.
  16. ^ Slater, Brady (June 1, 2019). "Twin Ports to Twin Cities rail regroups, aims at 2020". Duluth News Tribune. Retrieved June 4, 2019.
  17. ^ Moffett, Kaitlyn (February 10, 2020). "NLX project leaders request $40 million in state funding". KBJR. Archived from the original on April 26, 2020. Retrieved February 21, 2020.
  18. ^ LeBrun, T. A. (January 26, 2022). "Is Northern Lights Express regaining steam?". Isanti-Chisago County Star. Retrieved February 4, 2022.
  19. ^ Slater, Brady (February 3, 2022). "Passenger rail from Twin Ports to Twin Cities sees equal parts leverage, doubters". Duluth News Tribune. Retrieved February 4, 2022.
  20. ^ "Minnesota transportation bill approves funding for NLX". Global Railway Review. May 30, 2023. Retrieved May 30, 2023.
  21. ^ "Minneapolis to Duluth train awaits decision on federal funds". November 29, 2023.
  22. ^ "FY22 Corridor Identification and Development Program Selections" (PDF). railroads.dot.gov. Federal Railroad Administration. December 2023. p. 8. Retrieved December 9, 2023.
  23. ^ Levy, Paul (November 29, 2009). "Mpls.-to-Duluth rail price tag climbs to $1 billion". StarTribune. Retrieved December 15, 2009.
  24. ^ Levy, Paul (December 13, 2009). "MnDOT getting a line on Twin Cities-Duluth rail". StarTribune. Retrieved December 15, 2009.
  25. ^ "About - Northern Lights Express - MnDOT". Minnesota Department of Transportation. Retrieved November 28, 2022.
  26. ^ "Value Engineering in the Federal-Aid Highway Program" (PDF). Federal Highway Administration. March 28, 2007. Archived from the original (PDF) on August 4, 2009. Retrieved December 21, 2009.
  27. ^ "Interstate FAQ". Federal Highway Administration. Retrieved December 21, 2009.
  28. ^ TEMS, Inc. "Corridor Speed Options: 110-mph vs. 90-mph Evaluation" (PDF). Northern Lights Express.
  29. ^ Mike Gainor (May 4, 2010). "NLX board studies train speed choices". Retrieved May 21, 2010.
  30. ^ "National Train Timetables, Effective April 28, 1985 through October 26, 1985". 1985. Retrieved September 23, 2010.
  31. ^ a b Minnesota Department of Transportation (July 2009). Minneapolis-St. Paul Metro Area 2009 Railroad Volume and Speed Map (PDF) (Map). Minnesota Department of Transportation. Archived from the original (PDF) on May 19, 2011.
  32. ^ Cambridge Systematics, Inc. (July 31, 2009). "Minnesota Comprehensive Statewide Freight and Passenger Rail Plan: Freight Rail Supply and Demand (Draft Technical Memorandum 2)" (PDF). Minnesota Department of Transportation. Retrieved September 21, 2010.
  33. ^ "Minnesota Comprehensive Statewide Freight and Passenger Rail Plan: Freight and Passenger Rail System Planning (Draft Technical Memorandum 4)" (PDF). Cambridge Systematics. August 2009. Retrieved January 6, 2010.
  34. ^ "BNSF Easement Rights and Passenger Rail Capacity Improvements" (PDF). Minnesota Department of Transportation. September 15, 2009. Archived from the original (PDF) on September 2, 2012.

Read other articles:

Baye, Marne Koordinat: 48°51′20″N 3°45′54″E / 48.8556°N 3.765°E / 48.8556; 3.765NegaraPrancisArondisemenÉpernayKantonMontmort-LucyAntarkomuneCommunauté de communes de la Brie des ÉtangsKode INSEE/pos51042 /  Untuk pengertian lain, lihat Baye. Baye adalah komune di departemen Marne, Champagne-Ardenne, Prancis. Demografi Populasi historis Tahun JumlahPend.  ±%   482 —     393 —     Sumbe...

 

У этого топонима есть и другие значения, см. Бухарестская (значения). Бухарестская улица Бухарестская улица у пересечения с проспектом Славы Общая информация Страна Россия Город Санкт-Петербург Район Фрунзенский Протяжённость 8450 м Ширина 6 полос + трамвай Метро  Волко...

 

1974 World Sportscar Championship Previous 1973 Next 1975 The 1974 World Sportscar Championship season was the 22nd season of FIA World Sportscar Championship motor racing. It featured the 1974 World Championship for Makes [1] and FIA Cup for GT Cars [1] which were contested concurrently over a ten race series [1] from 25 April to 9 November 1974. The World Championship for Makes, which was open to Group 5 Sports Cars and Group 4 GT Cars,[2] was won by Matra ...

Provides integral formulas for all derivatives of a holomorphic function Not to be confused with Cauchy's integral theorem or Cauchy formula for repeated integration. Mathematical analysis → Complex analysisComplex analysis Complex numbers Real number Imaginary number Complex plane Complex conjugate Unit complex number Complex functions Complex-valued function Analytic function Holomorphic function Cauchy–Riemann equations Formal power series Basic theory Zeros and poles Cauchy's integral...

 

International cricket tour South Africa A cricket team in Sri Lanka in 2023    Sri Lanka A South Africa ADates 4 – 22 June 2023Captains Nipun Dananjaya Tony de ZorziFC seriesResult Sri Lanka A won the 2-match series 1–0Most runs Ramesh Mendis (186) Tristan Stubbs (129)Most wickets Lakshitha Manasinghe (12) Senuran Muthusamy (18)LA seriesResult South Africa A won the 3-match series 2–1Most runs Nishan Madushka (176) Tristan Stubbs (117)Most wickets Dilshan Madushanka (9) G...

 

Government agency in Connecticut Connecticut Department of TransportationAgency overviewFormed1965Preceding agencyConnecticut Highway DepartmentJurisdictionConnecticutHeadquarters2800 Berlin Turnpike, Newington, ConnecticutAgency executiveGarrett T. Eucalitto, CommissionerParent agencyState of ConnecticutWebsitect.gov/dot This article relies largely or entirely on a single source. Relevant discussion may be found on the talk page. Please help improve this article by introducing citations to a...

  لمعانٍ أخرى، طالع روزيتا (توضيح). روزيتا   المشغل وكالة الفضاء الأوروبية  سمي باسم حجر رشيد  تاريخ الإطلاق 2 مارس 2004[1]  موقع الإطلاق إيلا-3  [لغات أخرى]‏[2]  تاريخ الهبوط 30 سبتمبر 2016[3]  موقع الهبوط 67P/تشوريوموف-جيراسيمنكو  نقطة النهاي...

 

سفينداميو   تقسيم إداري البلد اليونان  [1] خصائص جغرافية إحداثيات 40°25′00″N 22°32′30″E / 40.41666667°N 22.54166667°E / 40.41666667; 22.54166667  الارتفاع 160 متر  السكان التعداد السكاني 935 (إحصاء السكان) (2011)  معلومات أخرى التوقيت ت ع م+02:00 (توقيت قياسي)،  وت ع م+03:00 (توقيت صيف...

 

DB-Baureihe 423/433 423 449 auf der Main-Weser-Bahn423 449 auf der Main-Weser-Bahn Nummerierung: 001/501–462/962 Anzahl: 462 Einheiten Hersteller: Adtranz, Alstom LHB, ABB, Bombardier Baujahr(e): 1998–2007 Achsformel: Bo’(Bo’) (2’) (Bo’)Bo’[1] Spurweite: 1435 mm (Normalspur) Länge über Kupplung: 67.400 mm[1] Höhe: 4.295 mm[1] Breite: 3.020 mm[2] Drehzapfenabstand: 15.140 mm (Endwagen)[2]15.460 mm (Mittelwagen)[2] ...

Louise Scheppler, 1824 Louise Scheppler, auch Luise Scheppler (* 4. November 1763 in Bellefosse, Elsass; † 25. Juli 1837 in Waldersbach, Elsass) war eine „Kleinkinderschullehrerin“ und seit 1778 die engste Mitarbeiterin von Pfarrer Johann Friedrich Oberlin. Inhaltsverzeichnis 1 Leben 2 Ehrungen und Benennungen 2.1 Gedenktag 2.2 Louise Scheppler als Namensgeberin 3 Literatur 4 Weblinks 5 Einzelnachweise Leben Louise Scheppler im Scherenschnitt, 1786 geschaffen von Johann Friedrich Oberli...

 

هذه المقالة يتيمة إذ تصل إليها مقالات أخرى قليلة جدًا. فضلًا، ساعد بإضافة وصلة إليها في مقالات متعلقة بها. (ديسمبر 2018) منظمة البقاء على قيد الحياةالشعارالتاريخالتأسيس 1984 الإطارالنوع منظمة الوضع القانوني association under the French law of 1901 (en) البلد  فرنسا التنظيمموقع الويب survie.org تعد...

 

Francesco Fidanza (Roma, 1747 – Milano, 4 febbraio 1819) è stato un pittore italiano. Francesco Fidanza, Paesaggio Indice 1 Biografia 1.1 A Parigi 1.2 A Milano 1.3 Altri dipinti 2 Note 3 Bibliografia 4 Altri progetti 5 Collegamenti esterni Biografia Francesco Fidanza era figlio di Filippo (1720 c.-1790), pittore originario di Città di Castello che fu allievo di Marco Benefial. Il fratello Gregorio (1759-1823), anch'egli pittore di paesaggi, fu discepolo di Claude Lorrain, ma i suoi dipint...

Kiri Die LinkeKetua umum Janine Wissler Martin Schirdewan Dibentuk16 Juni 2007 (2007-06-16)Digabungkan dariPDSWASGKantor pusatKarl-Liebknecht-HausKl. Alexanderstraße 28D-10178 BerlinSurat kabarNeues DeutschlandWadah pemikirRosa Luxemburg FoundationSayap pelajarDie Linke.SDSSayap pemudaPemuda Kiri SolidKeanggotaan (2022) 60,681IdeologiSosialisme demokratikPopulisme sayap kiri[1]Antikapitalisme[2][3]Antimiliterisme[2][4]Posisi politikSayap...

 

French writer (1619–1692) This article has multiple issues. Please help improve it or discuss these issues on the talk page. (Learn how and when to remove these template messages) This article relies largely or entirely on a single source. Relevant discussion may be found on the talk page. Please help improve this article by introducing citations to additional sources.Find sources: Gédéon Tallemant des Réaux – news · newspapers · books · scholar ·...

 

Kue Balikuhai yang disajikan di daun pisang Balikuhai adalah nama kue khas dari kabupaten Hulu Sungai Tengah, Kalimantan Selatan, yang bentuknya seperti kue wafel. Perbedaan Balikuhai dengan wafel adalah penggunaan tepung yang digunakan, jika wafel menggunakan tepung terigu maka kue Balikuhai menggunakan tepung beras. Sehingga menghasilkan tekstur yang tidak terlalu sepadat wafel. Hal ini merupakan alkuturasi kuliner dimana resep aslinya yang dari peninggalan Belanda yang sempat menduduki wil...

Canadian actress and journalist Nicole Germain in 1946 Nicole Germain, C.M. (born Marcelle Landreau; November 29, 1917 – February 11, 1994) was a Canadian actress in Quebec radio and film in the 1940s and 1950s and later as a journalist. In 1974, she was named a member of the Order of Canada. Personal life Germain was born Marcelle Landreau. Her father was George Landreau, director of the Montreal Conservatory.[1] She was also niece to Chief Justice Rinfret.[2] She studied a...

 

For other people named William Troy, see William Troy (disambiguation). The Reverend William TroyPersonal detailsBorn10 March 1827Essex County, VirginiaDied17 November 1905Camden, New Jersey The Reverend William Troy (10 March 1827 - 17 November 1905) was a Baptist minister and writer associated with the Underground Railroad. Life Troy was born on 10 March 1827 in Essex County, Virginia. His mother was a free black woman and she married, then bought and set free, her husband.[1] Troy ...

 

Assault Support Patrol Boat ASPB in South Vietnam c.1968 Class overview NameASPB (Assault Support Patrol Boat) Operators  United States Navy Republic of Vietnam Navy Khmer National Navy Completed86 General characteristics TypeRiverine patrol boat Length50 ft (15 m) Propulsion2 × 430hp General Motors 12V71 diesel engines Speed14.8 knots Range130 nautical miles (240 km; 150 mi) Complement5 Armament two Mk 48 turrets with either 20 mm cannon or .50 cal machine guns two ...

هذه صفحة توثيق قالب:موقع مدينة 2 الفرعية، لشرح القالب وتصنيفه، وهي لا تدخل في استخدامه. استعمال {{موقع مدينة 2 | المركز = | شمال = | شمال شرقي = | ENE = | شرق = | ESE = | جنوب شرقي = | جنوب = | جنوب غربي = | WSW = | غرب = | WNW = | شمال غرب = | ملف = }} انظر أيضا

 

HIeronimus De Viris Illustribus (Perihal Tokoh-tokoh Terkemuka) adalah kumpulan pendek biografi 135 penulis, yang ditulis dalam bahasa Latin, pada abad ke-4 oleh Pastor Hieronimus (Jerome) dari Gereja Latin. Ia menyelesaikan pekerjaan ini di Betlehem pada tahun 392-3 M.[1] Karya ini terdiri dari prolog (kata pengantar) ditambah 135 bab, masing-masing terdiri dari sebuah biografi singkat. Hieronimus sendiri adalah subjek dari bab terakhir. Versi Yunani buku ini, mungkin oleh Sophronius...

 

Strategi Solo vs Squad di Free Fire: Cara Menang Mudah!