Algiers Metro

Algiers Metro
Tafourah - Grande Poste station
Tafourah - Grande Poste station
Overview
Native nameمترو الجزائر العاصمة
Adubrid en Dzayer
LocaleAlgiers, Algeria
Transit typeRapid transit
Number of lines1[1]
(2 planned)[2]
Number of stations19[3]
Annual ridership40,032,641 (2018)[4]
Websitewww.metroalger-dz.com
Operation
Began operation1 November 2011; 13 years ago (2011-11-01)[2]
Operator(s)RATP El-Djazaïr (RATP El Djazaïr [fr])
Technical
System length18.5 km (11.5 mi)[3]
Track gauge1,435 mm (4 ft 8+12 in) standard gauge[5]
Electrification750 V DC third rail[5]
System map

The Algiers Metro (Arabic: مترو الجزائر العاصمة) is a rapid transit system that serves Algiers, the capital of Algeria. Originally designed in the 1970s, it opened in 2011 after decades of delays due to financial difficulties and security issues.[1][2] The Algiers Metro was the second metro system to open in Africa, after the Cairo Metro.[6]

The first phase of Line 1, "Haï el Badr"–"Tafourah-Central Post Office", which had a length of 9.2 kilometres (5.7 mi) and comprised 10 stations, opened for public service on 1 November 2011.[1] A 4-kilometre (2.5 mi) extension from "Haï el Badr" to "El Harrach Centre" opened for commercial service on 4 July 2015 after test runs in June.[7][8]

History

Haï El Badr station
Inside the train

During the 1970s, the promoters of the Algiers rapid transit subway project envisioned a 64 km (40 mi) network. The project was officially inaugurated in 1982, with technical studies completed in 1985. Authorities retained a German company and a Japanese specialist for building the network. The collapse of oil prices in the 1980s considerably affected the Algerian state's ability to continue funding the project. Authorities discussed the possibility of folding the subway development programme into other mass-transit projects but eventually decided to continue with the original Metro program, albeit slowly.

In 1988–89, Algeria awarded construction contracts to two national companies: COSIDER and GENISIDER.[9] Neither was experienced in running large urban transit development projects. Construction encountered financial and political difficulties, with only four stations being constructed in 15 years. Moreover, the Algiers soil is difficult to dig in, and the city's topography is irregular. Work did not advance significantly for many years.

In 1994, the first 450 m (1,476 ft) long section, called Emir-Abdelkader, was completed. Another 650 m (2,133 ft) section, connecting the Central Post Office to Khélifa-Boukhalfa, was completed soon after. In 1999, the Metro of Algiers Company (EMA) invited international companies to participate in a tender offering, resulting in two new contractors being added to the project: French Systra-Sgte for project management, and Agéro-German GAAMA [who?]for construction and completion, within 38 months, of the civil engineering tasks and earthworks.

In 2003, benefiting from the return of economic stability and improved security, the government increased funding and introduced a new organisational and operational structure.

In January 2006, further changes were introduced to the project, with integrated systems development handed to Siemens Transportation Systems. This included the installation of fixed material, signals and electrification. Vinci was responsible for civil engineering, and the Spanish company Construcciones y Auxiliar de Ferrocarriles (CAF) was to deliver a new set of rolling stock, including 14 trains of 6 cars each. The network would use the Trainguard MT CBTC technology, which had already been implemented on line 1 and line 14 of the Paris Métro.[10]

System

With a length of 9.2 kilometres (5.7 mi), the first section of Line 1 to open included ten stations, connecting Tafourah–Grande Poste to Haï El Badr.[1] Nine of the ten stations are underground with two central tracks flanked by two 115 metres (377 ft) long side platforms. Only the Haï El Badr terminus station is on the surface and it has three tracks and two island platforms.

  • The El Hamma - Haï El Badr section, with its 4 stations and 17 other works for ventilation and cables was carried out within 38 months. Civil engineering work and rail laying were officially completed on 30 June 2007.
  • The installation and the welding of 23 kilometres (14 mi) of tracks were started in April 2007 by the French company South-western Travaux France (TSO) with the first metro car to be delivered to Algiers by December 2007.

In July 2015, this was supplemented by the opening of the 4-kilometre (2.5 mi), four-station expansion from "Haï el Badr" to "El Harrach Centre". The system now serves 14 stations, over a total route length of approximately 13.5 kilometres (8.4 mi).

Stations

Name Community Notes
Place des Martyrs Casbah of Algiers 2018
Ali Boumendjel Alger Centre
Tafourah - Grande Poste 2011
Khelifa Boukhalfa
1er Mai Sidi M'Hamed
Aïssat Idir
Hamma Belouizdad
Jardin d'essai
Les Fusillés Hussein Dey
Cité Amirouche
Cité Mer et Soleil
Haï El Badr El Magharia
El Harrach Gare Bourouba 2015
El Harrach Centre El Harrach
Bachdjarah - Tennis Bachdjerrah
Bachdjarah Bachdjerrah / Bourouba
Les Ateliers Bachdjerrah 2018
Gué de Constantine Djasr Kasentina
Ain Naadja

Operations

Ticket

The total cost of the first phase of line 1 rose to 77 billion DZD (900 million euros), consisting of DZD 30 billion for civil engineering and DZD 47 billion for the equipment.[citation needed]

  • 14 six-car trains are being used. Each train is 108m in length with 208 seats and can transport 1,216 people.
  • The metro line can move 41,000 passengers per hour, the equivalent of 150 million passengers per year, with a headway of under 2 minutes. Trains can travel at speeds of up to 70 km/h (43 mph), and the line is open from 5 a.m. to 11 p.m.
  • The metro's daily operation is the responsibility of the RATP Group, which was awarded the contract in August 2007.

Extensions

Public transport of Algiers with planned Metro extensions

Invitations to tender were launched for the construction of a 4 km (2.5 mi) section between Bachdjarrah and El Harrach composed of 4 stations and one viaduct 250 m (820 ft) above the access road to the Ouchaïah Wadi motorway. It opened for public service on 4 July 2015.[7][8]

  • The Gaama group which carried out the first section quoted 250 million euros including the construction of a multimodal station (subway/train/taxis) at the El Harrach railway station.

Two other extensions to Line 1 had a planned public opening in 2017:[8]

  • a branch line from Haï El Badr to Aïn Naâdja.
  • an extension north from Tafourah Grande Poste to Place des Martyrs

Network map

Map


See also

References

  1. ^ a b c d "Alger metro inaugurated". Railway Gazette International. 31 October 2011. Retrieved 14 September 2013.
  2. ^ a b c "Maghreb's first metro system opens in Algeria". Radio France International. 31 October 2011. Retrieved 14 September 2013.
  3. ^ a b "Le Président Bouteflika inaugure deux nouvelles extensions du Métro d'Alger". aps.dz. Retrieved 10 April 2018.
  4. ^ "Statistiques voyageur" [Passenger statistics] (in French). EMA - Entreprise Metro d’Alger. Archived from the original on 22 July 2017.
  5. ^ a b "Rail projects in Algeria: Focus on tramway systems". Global Mass Transit. 1 February 2013. Archived from the original on 8 October 2021. Retrieved 23 February 2018.
  6. ^ "Metro systems: Going Underground". The Economist. 5 January 2013. Retrieved 14 September 2013.
  7. ^ a b "Algiers Metro: New line Hai El Badr-El Harrach operational in July". Algeria Press Service. 14 June 2015. Archived from the original on 18 November 2016. Retrieved 6 August 2015.
  8. ^ a b c "Alger metro extends". Railway Gazette International. 6 July 2015. Archived from the original on 8 October 2018. Retrieved 7 August 2015.
  9. ^ Le Chemin de Fer en Algérie : Pour une dynamique nouvelle, Rapport 1998, Annexe 4 - Conseil National Economique et Social, Commission de l’Aménagement du Territoire et de l’Environnement Archived 10 December 2011 at the Wayback Machine (Archived)
  10. ^ "Alger" [Algiers] (in French). Siemens. Retrieved 23 February 2018.